  • 31the following types of costs are relevant to making a financial decision except:

    A.opportunity costs

    B.direct costs

    C.sunk cost

    D.unavoidable costs

    E.none of the above

    开始考试练习点击查看答案
  • 32the standard types of communication include all but

    A.written

    B.verbal

    C.telepathic

    D.nonverbal

    E.none of the above

    开始考试练习点击查看答案
  • 33(    ) of the extra costs of the project can often be attributed to a lack of quality.

    A.0.12

    B.0.15

    C.0.2

    D.0.25

    E.less than 10%

    开始考试练习点击查看答案
  • 34a budget estimate should give the manager cost data accurate to within:

    A.-5 to +10 percent of actual cost

    B.-25 to +75 percent of actual cost

    C.-30 to +75 percent of actual cost

    D.-10 to +25 percent of actual cost

    E.none of the above

    开始考试练习点击查看答案