  • 21project life cycles provide a better means of measurement of progress and control. the four phases of a project are conceptual development,(    ), (    ), and (    ).

    A.preliminary planning, detail planning, closeout

    B.implementation, reporting, termination

    C.development, implementation, termination

    D.execution, reporting, finishing

    E.implementation, termination, post-audit review

    开始考试练习点击查看答案
  • 22response planning is the responsibility of the functional areas and considers

    A.mitigation.

    B.deflection.

    C.contingency planning.

    D.unforeseen occurrences.

    E.all of the above.

    开始考试练习点击查看答案
  • 23the definitive terms of a contract are written during which of the following contract phases、

    A.contract phase

    B.post-award phase

    C.award phase

    D.pre-award phase

    E.requirement phase

    开始考试练习点击查看答案
  • 24the sending or conveying of information from one place to another is the process of

    A.networking

    B.transmitting

    C.interacting

    D.promoting

    E.interfacing

    开始考试练习点击查看答案
  • 25which of the following types of cost are relevant to making financial decisions:

    A.sunk cost

    B.opportunity cost

    C.material cost

    D.a and c only

    E.b and c only

    开始考试练习点击查看答案
  • 26in preparing a good project definition, experienced project managers will:

    A.concentrate mainly on the end product rather than costs or benefits. these come later.

    B.realize that only the "tip of the iceberg" may be showing. as a project manager, you must get beneath it.

    C.understand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.

    D.try to convert objectives into quantifiable terms.

    E.all of the above

    开始考试练习点击查看答案
  • 27in which of the following is the cost of risk hidden by the contractor、

    A.firm fixed price contract

    B.fixed price plus incentive

    C.cost plus fixed price

    D.cost plus percentage of cost

    E.a and b

    开始考试练习点击查看答案
  • 28management of a certain building was receiving complaints about slow elevator service. the solution adopted was to add mirrors in thelobbies to reduce boredom while passengers waited. this is an example of (    ) .

    A.kepner-tregoe method

    B.potential problem analysis

    C.decision analysis

    D.creative problem solving

    E.none of the above

    开始考试练习点击查看答案
  • 29pure risk differs from business risks because pure risk's (    ) .

    A.include chances of both profit or loss associated with the business.

    B.include chances of loss and no chances for profit associated with the business.

    C.must incur personal loss with business liability.

    D.must incur business liability associated with loss of pure profit.

    E.b and c

    开始考试练习点击查看答案
  • 30the actual configuration of a pert/cpm network (    ) the amount of resources that can be devoted to the project.

    A.increases.

    B.is not affected by

    C.does not require

    D.is heavily dependent upon

    E.is the only means of determining

    开始考试练习点击查看答案