位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(21,22)

a budget estimate should give the manager cost data accurate to within:

发布时间:2024-07-09

A.-5 to +10 percent of actual cost

B.-25 to +75 percent of actual cost

C.-30 to +75 percent of actual cost

D.-10 to +25 percent of actual cost

E.none of the above

试卷相关题目

  • 1(    ) of the extra costs of the project can often be attributed to a lack of quality.

    A.0.12

    B.0.15

    C.0.2

    D.0.25

    E.less than 10%

    开始考试点击查看答案
  • 2the standard types of communication include all but

    A.written

    B.verbal

    C.telepathic

    D.nonverbal

    E.none of the above

    开始考试点击查看答案
  • 3the following types of costs are relevant to making a financial decision except:

    A.opportunity costs

    B.direct costs

    C.sunk cost

    D.unavoidable costs

    E.none of the above

    开始考试点击查看答案
  • 4the actual configuration of a pert/cpm network (    ) the amount of resources that can be devoted to the project.

    A.increases.

    B.is not affected by

    C.does not require

    D.is heavily dependent upon

    E.is the only means of determining

    开始考试点击查看答案
  • 5pure risk differs from business risks because pure risk's (    ) .

    A.include chances of both profit or loss associated with the business.

    B.include chances of loss and no chances for profit associated with the business.

    C.must incur personal loss with business liability.

    D.must incur business liability associated with loss of pure profit.

    E.b and c

    开始考试点击查看答案
返回顶部