- 31which is not part of the purchasing cycle、
A.defined need
B.transmit need
C.inspection
D.prepare and issue purchase order
E.a and d
开始考试练习点击查看答案 - 32a network has been developed with resources from six different departments. one of the six departments has just informed you that they canincrease the number of employees from 5 to 8. this will result in:
A.a shortening of the critical path.
B.a shortening of the noncritical path.
C.a decrease in the total cost of the project.
D.an increase in the cost of the project.
E.a through d are possible based upon where the resources are deployed.
开始考试练习点击查看答案 - 33conflict management requires problem-solving. which of the following is often referred to as a problem-solving technique and usedextensively in conflict resolution、
A.confrontation
B.compromise
C.smoothing
D.forcing
E.withdrawal
开始考试练习点击查看答案 - 34cost reimbursable contracts are equivalent to:
A.cost plus contracts
B.fixed plus contracts
C.progress payment contracts
D.back charge contracts
E.none of the above.
开始考试练习点击查看答案 - 35in project-driven companies, costs are usually billed againest the project based upon:
A.the burdened labor rate of the actual employees who performed the work.
B.the burdened labor rate of the line organization average salary.
C.the burdened labor rate of the company average salary.
D.the burdened labor rate of the average salary of the project team members.
E.none of the above.
开始考试练习点击查看答案 - 36project risk management is based on which of the following premises:
A.the future is unknown.
B.unknowns can result in risks or opportunities.
C.we cannot control risk events.
D.project risk impact can be measured and controlled
E.all of the above.
开始考试练习点击查看答案 - 37the project manager that allows and supports group discussions and decision making is called a(n) ( ) manager.
A.autocratic
B.consultant autocratic
C.consensus
D.shareholder
E.none of the above.
开始考试练习点击查看答案 - 38what is the purpose of the project plan、
A.to document the preliminary estimates.
B.to document the definitive estimates.
C.to document the budgetary estimates.
D.to document parametric estimates.
E.to document order of magnitude estimates.
开始考试练习点击查看答案 - 39management has decided to "crash" a project in order to avoid penalty payments for late deliveries. to crash the project, either overtime oradditional resources should be assigned to:
A.all activities.
B.only those activities with the longest time durations.
C.those activities on the critical path begining with the longest time duration activities.
D.those activities with the greatest degree of risk.
E.none of the above.
开始考试练习点击查看答案
最新试卷
高中教育高考语文(重庆卷)2013年普通高等学校招生全国统一考试
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题9
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题8
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题6
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题4
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题3
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题2
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题1
类别:学历类其它高中教育高考语文高中语文课课练(5)
类别:学历类其它高中教育高考语文高中语文总复习 经典易错题会诊与命题角度
类别:学历类其它