- 21the type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing thatproject. for a firm fixed price contract, payment for risk ( ) .
A.is accomplished by paying the actual costs to the contractor.
B.is accomplished by paying the contractor for his costs plus a fixed fee (profit).
C.is an undisclosed contingency in the contractor's bi
D.D.is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.
E.b and c
开始考试练习点击查看答案 - 22which is not an element of procurement management、
A.purchasing
B.expenditure
C.marketing
D.inspection
E.b and d
开始考试练习点击查看答案 - 23which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle、
A.0.05
B.0.1
C.0.15
D.0.25
E.0.5
开始考试练习点击查看答案 - 24bar charts are most appropriate for:
A.comparing actual to planned performance to each activity.
B.showing slack time.
C.showing critical path dependencies.
D.showing which activities can be rearranged in parallel.
E.all of the above.
开始考试练习点击查看答案 - 25formal authority is often referred to as legitimate power. which two other forms of power are also considered to be legitimate power、
A.reward and penalty
B.reward and referent
C.referent and expert
D.expert and reward
E.penalty and referent
开始考试练习点击查看答案 - 26power games, withholding information, and hidden agendas are examples of-.
A.noise
B.communication barriers
C.indirect communication
D.mixed messages
E.all of the above
开始考试练习点击查看答案 - 27scope management is:
A.a project control function.
B.employs change control.
C.a work authorization process.
D.considers cost, quality and schedul
E.E.all of the above.
开始考试练习点击查看答案 - 28the most common method for pricing out non-burdened labor hours for a three year project would be to:
A.price out the hours at the actual salary of the people to be assigned.
B.price out the work using a company-wide average labor rate.
C.price out the work using a functional group average labor rate.
D.B.price out the work using a company-wide average labor rat
E.C.price out the work using a functional group average labor rate.D.all of the above.E.a and b only.
开始考试练习点击查看答案 - 29the principles of risk management should be followed only for:
A.complex projects
B.simple projects
C.large projects
D.a and c
E.all of the above.
开始考试练习点击查看答案 - 30utility theory:
A.considers the risk propensity of the decision makers.
B.is based on proven statistical methods.
C.deals with the usefulness of the end product.
D.is a key element of iso 9000
E.b and c
开始考试练习点击查看答案
最新试卷
高中教育高考语文(重庆卷)2013年普通高等学校招生全国统一考试
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题9
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题8
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题6
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题4
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题3
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题2
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题1
类别:学历类其它高中教育高考语文高中语文课课练(5)
类别:学历类其它高中教育高考语文高中语文总复习 经典易错题会诊与命题角度
类别:学历类其它