what is the purpose of the project plan、

发布时间:2024-07-09

A.to document the preliminary estimates.

B.to document the definitive estimates.

C.to document the budgetary estimates.

D.to document parametric estimates.

E.to document order of magnitude estimates.

试卷相关题目

  • 1the project manager that allows and supports group discussions and decision making is called a(n) (    ) manager.

    A.autocratic

    B.consultant autocratic

    C.consensus

    D.shareholder

    E.none of the above.

    开始考试点击查看答案
  • 2project risk management is based on which of the following premises:

    A.the future is unknown.

    B.unknowns can result in risks or opportunities.

    C.we cannot control risk events.

    D.project risk impact can be measured and controlled

    E.all of the above.

    开始考试点击查看答案
  • 3in project-driven companies, costs are usually billed againest the project based upon:

    A.the burdened labor rate of the actual employees who performed the work.

    B.the burdened labor rate of the line organization average salary.

    C.the burdened labor rate of the company average salary.

    D.the burdened labor rate of the average salary of the project team members.

    E.none of the above.

    开始考试点击查看答案
  • 4cost reimbursable contracts are equivalent to:

    A.cost plus contracts

    B.fixed plus contracts

    C.progress payment contracts

    D.back charge contracts

    E.none of the above.

    开始考试点击查看答案
  • 5conflict management requires problem-solving. which of the following is often referred to as a problem-solving technique and usedextensively in conflict resolution、

    A.confrontation

    B.compromise

    C.smoothing

    D.forcing

    E.withdrawal

    开始考试点击查看答案
  • 6management has decided to "crash" a project in order to avoid penalty payments for late deliveries. to crash the project, either overtime oradditional resources should be assigned to:

    A.all activities.

    B.only those activities with the longest time durations.

    C.those activities on the critical path begining with the longest time duration activities.

    D.those activities with the greatest degree of risk.

    E.none of the above.

    开始考试点击查看答案