位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(3.4)

手机扫码关注微信
随时随地刷题

项目管理师PMP美国项目管理PMPPMP认证考试练习题(3.4)

推荐等级:
  • 卷面总分:0分
  • 试卷类型:模拟试题
  • 测试费用:¥5.00
  • 试卷答案:
  • 练习次数:0
  • 作答时间:0分钟

试卷介绍

试卷预览

  • 31activities with zero time duration are referred to as:

    A.critical path activites.

    B.noncritical path activities.

    C.slack time activities.

    D.dummies

    E.none of above.

    开始考试练习点击查看答案
  • 32for a given characteristic in a construction process, the standard deviation associated with production variation is 0.8", and the standard deviation associated with measurement variation is 0.6". the total standard deviation for thischaracteristic is:

    A.1.4"

    B.1.2".

    C.1.0"

    D.0.8"

    E.0.2"

    开始考试练习点击查看答案
  • 33project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:

    A.overhead rates, labor rates and material costs.

    B.overhead rates, schedule slippages, and rework.

    C.rework, cost-of-living adjustments, and overtime.

    D.material costs, shipping cost, and scope changes.

    E.labor rates, material costs, and cost reporting.

    开始考试练习点击查看答案
  • 34selective perception is (    ) of new conflicting information that may result, in a breakdown in communication.

    A.encoding

    B.blocking out

    C.transmission

    D.acceptance

    E.decoding

    开始考试练习点击查看答案
  • 35the work breakdown structure (wbs) is an excellent tool for objective control and evaluation. which of the following is generally notvalidated through the wbs、

    A.time, schedule and cost.

    B.management coordination and organization structuring.

    C.work methods and accountability.

    D.quality of work.

    E.risk and impact decision-making.

    开始考试练习点击查看答案
  • 36when working in an environment that uses learning curves, the most effective plan for creating the perception that pay is related toperformance is to provide the team members with an individual salary plus bonus based upon

    A.individual productivity

    B.cost effectiveness

    C.group or team productivity

    D.rating system developed by the project manager

    E.all of the above

    开始考试练习点击查看答案
  • 37which of the following is not part of the acquisition process:

    A.source selection

    B.invitation to bid

    C.contract award

    D.notice to proceed

    E.all of the above are parts of the acquisition process.

    开始考试练习点击查看答案
  • 38an individual who is working on the satisfaction of physiological needs has essentially satisfied which needs、

    A.safety

    B.empowerment/authority

    C.esteem

    D.self-actualization

    E.none of the above

    开始考试练习点击查看答案
  • 39in the pdm, common constraints include:

    A.start-to-start

    B.finish-to-start

    C.finish-to-finish

    D.b and c only

    E.a, b, and c

    开始考试练习点击查看答案
  • 40scope reporting is the timely determination, (    ), and (    ) of project progress, status data, and transforming this into structureddocumentation (reports) necessary to judge project performance (reporting on work packages).

    A.recording, accumulation.

    B.recording, graphical display.

    C.accumulation, graphical display.

    D.graphical display, interpretation.

    E.interpretation, analysis.

    开始考试练习点击查看答案
 4/4   首页 上一页 2 3 4
返回顶部