位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(3.4)

for a given characteristic in a construction process, the standard deviation associated with production variation is 0.8", and the standard deviation associated with measurement variation is 0.6". the total standard deviation for thischaracteristic is:

发布时间:2024-07-09

A.1.4"

B.1.2".

C.1.0"

D.0.8"

E.0.2"

试卷相关题目

  • 1activities with zero time duration are referred to as:

    A.critical path activites.

    B.noncritical path activities.

    C.slack time activities.

    D.dummies

    E.none of above.

    开始考试点击查看答案
  • 2to calculate the expected value of an outcome:

    A.divide the value of each outcome by its probability, then add the results.

    B.divide the value of the desired outcome by the value all possible outcomes

    C.multiply the value of each outcome by its probability, then add the results

    D.use linear regression to assess the expected value of the outcome

    E.b and d only

    开始考试点击查看答案
  • 3the three most common types of project cost estimates are:

    A.order of magnitude, parametric, and budget.

    B.parametric, definitive and top down.

    C.order of magnitude, definitive and bottom up.

    D.order of magnitude, budget and definitiv

    E.E.analogy, parametric and top down.

    开始考试点击查看答案
  • 4the scope baseline once established and approved, is used:

    A.as the basis for making future decisions.

    B.to accomplish verification measures.

    C.to evaluate potential changes.

    D.all of the abov

    E.E.a and c only.

    开始考试点击查看答案
  • 5project managers that are available to answer questions, provide guidance when need, and generally do not interfere with day-to-day activitieshave a(n) (    ) managerial style.

    A.autocratic

    B.conciliatory

    C.ethical

    D.facilitative

    E.judicial

    开始考试点击查看答案
  • 6project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:

    A.overhead rates, labor rates and material costs.

    B.overhead rates, schedule slippages, and rework.

    C.rework, cost-of-living adjustments, and overtime.

    D.material costs, shipping cost, and scope changes.

    E.labor rates, material costs, and cost reporting.

    开始考试点击查看答案
  • 7selective perception is (    ) of new conflicting information that may result, in a breakdown in communication.

    A.encoding

    B.blocking out

    C.transmission

    D.acceptance

    E.decoding

    开始考试点击查看答案
  • 8the work breakdown structure (wbs) is an excellent tool for objective control and evaluation. which of the following is generally notvalidated through the wbs、

    A.time, schedule and cost.

    B.management coordination and organization structuring.

    C.work methods and accountability.

    D.quality of work.

    E.risk and impact decision-making.

    开始考试点击查看答案
  • 9when working in an environment that uses learning curves, the most effective plan for creating the perception that pay is related toperformance is to provide the team members with an individual salary plus bonus based upon

    A.individual productivity

    B.cost effectiveness

    C.group or team productivity

    D.rating system developed by the project manager

    E.all of the above

    开始考试点击查看答案
  • 10which of the following is not part of the acquisition process:

    A.source selection

    B.invitation to bid

    C.contract award

    D.notice to proceed

    E.all of the above are parts of the acquisition process.

    开始考试点击查看答案
返回顶部