  • 11the profitability and technical data studies are provided in report format to owners and funders for acceptance. this type of report, used to solicit funding, is referred to as a(n) (    ).

    A.project feasibility study.

    B.economic evaluation analysis.

    C.risk management manual.

    D.prospectus.

    E.none of the above

    开始考试练习点击查看答案
  • 12which of the following constitute juran's "quality trilogy":

    A.planning, inspection, control.

    B.planning, improvement, control.

    C.planning, organization, control.

    D.product, price, customer.

    E.design, build, deliver.

    开始考试练习点击查看答案
  • 13which of the following is most closely associated with business risk:

    A.profit and loss

    B.personnel turnover

    C.workmen's compensation

    D.liability insurance

    E.all of the above.

    开始考试练习点击查看答案
  • 14which of the following types of contracts is equivalent to a cost plus contract:

    A.fixed firm price

    B.cost reimbursable

    C.fixed price plus incentive fee

    D.progress payments

    E.all of the above.

    开始考试练习点击查看答案
  • 15a project manager recently rewarded an individual with a promotion that carried with it a very small salary increase but substantially moreresponsibility. the project manager appears to be appealing to the employee's (    ) need.

    A.monetary

    B.physiological

    C.esteem

    D.self-actualization

    E.team-building

    开始考试练习点击查看答案
  • 16most project (and non-project) managers prefer (    ) communications.

    A.oral

    B.written

    C.upward

    D.downward

    E.lateral

    开始考试练习点击查看答案
  • 17on a precedence diagram, the arrow between two boxes is called:

    A.an activity.

    B.a constraint.

    C.an event.

    D.the critical path.

    E.none of above.

    开始考试练习点击查看答案
  • 18quality control charts show a characteristic of the product or service against:

    A.the specification limits.

    B.customer requirements.

    C.control limits based on three standard deviations in each direction.

    D.control limits based on six standard deviations in each direction.

    E.a and d only

    开始考试练习点击查看答案
  • 19the identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives areindentified in the (    ) phase of the project but first documented in the project (    ).

    A.conceptual, charter/baseline.

    B.conceptual, master schedule.

    C.development, charter/baseline.

    D.development, master schedul

    E.E.development, masterplan.

    开始考试练习点击查看答案
  • 20the work breakdown structure, the work packages, and the company's accounting system are tied together through the:

    A.code of accounts.

    B.overhead rates.

    C.budgeting system.

    D.capital budgeting process.

    E.all of the above.