going from level 2 to level 4 in the work breakdown structure will result in

发布时间:2024-07-09

A.less estimating accuracy

B.better control of the project

C.lower status reporting costs

D.a greater likelihood that something will fall through the cracks

E.none of the above

试卷相关题目

  • 1the receiver filters messages based on all but the following:

    A.language

    B.distance

    C.culture

    D.knowledge

    E.authority/reputation

    开始考试点击查看答案
  • 2the net present value of $110 one year from now at 10% is:

    A.100

    B.120

    C.121

    D.$100 less taxes

    E.$100 less taxes and interest

    开始考试点击查看答案
  • 3situations calling for a matrix organization include outside pressure for dual focus, (    ) andpressure for high information processingcapability.

    A.pressure for clear accountability

    B.pressure for reduced duplication of effort

    C.pressure for shared resources

    D.pressure for formalized communication

    开始考试点击查看答案
  • 4quality control is normally performed by the (    ) .

    A.qa personnel

    B.project team

    C.operating personnel

    D.project management

    E.none of the above.

    开始考试点击查看答案
  • 5graphical displays of accumulated cost and labor hours, plotted as a function of time, are called:

    A.variance reports

    B.s curves

    C.trend analysis

    D.earned value reporting

    E.baseline control

    开始考试点击查看答案
  • 6on november 1, $1000 worth of work on task a was supposed to have been done (bcws); however, the bcwp was $850. calculate theschedule variance:

    A.-100

    B.100

    C.-150

    D.150

    E.0.85

    开始考试点击查看答案
  • 7the quality risk (    ) .

    A.is minimized through continuous monitoring.

    B.is considered a long term risk.

    C.will be reflected in the in-service life of the project result.

    D.b and c

    E.all of the above.

    开始考试点击查看答案
  • 8the act of conducting or supervising the exchange of information is:

    A.consulting

    B.project management

    C.communications management

    D.communications enhancement

    E.none of the above

    开始考试点击查看答案
  • 9the core function of the project manager is

    A.systems design

    B.client interfacing

    C.quality assurance

    D.integration

    开始考试点击查看答案
  • 10the future value of an annual income flow of $1000 for 2 years at 10% is:

    A.2200

    B.2280

    C.2300

    D.2310

    E.none of the above

    开始考试点击查看答案