quality control is normally performed by the (    ) .

发布时间:2024-07-09

A.qa personnel

B.project team

C.operating personnel

D.project management

E.none of the above.

试卷相关题目

  • 1graphical displays of accumulated cost and labor hours, plotted as a function of time, are called:

    A.variance reports

    B.s curves

    C.trend analysis

    D.earned value reporting

    E.baseline control

    开始考试点击查看答案
  • 2a warranty may not be a remedy for products delivered unfit when (    ) .

    A.the pm has knowledge of the product, inspected it without relying on the seller's skill

    B.the products delivered comply with the plans and specifications of the client

    C.the plans and specifications produced by the seller match the completed product.

    D.a and b

    E.none of the above.

    开始考试点击查看答案
  • 3a plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. calculate the variance:

    A.0.015

    B.0.33

    C.0.75

    D.0.67

    E.none of the above.

    开始考试点击查看答案
  • 4which of the following depreciation methods provides for accelerated depreciation of an asset:

    A.double declining balance.

    B.straight line.

    C.exponential depreciation

    D.double sum of the years digits

    E.double increasing balance

    开始考试点击查看答案
  • 5the statement of work (sow) is developed during the (    ) cycle.

    A.award

    B.solicitations

    C.requirements

    D.contractual

    E.requisitions

    开始考试点击查看答案
  • 6situations calling for a matrix organization include outside pressure for dual focus, (    ) andpressure for high information processingcapability.

    A.pressure for clear accountability

    B.pressure for reduced duplication of effort

    C.pressure for shared resources

    D.pressure for formalized communication

    开始考试点击查看答案
  • 7the net present value of $110 one year from now at 10% is:

    A.100

    B.120

    C.121

    D.$100 less taxes

    E.$100 less taxes and interest

    开始考试点击查看答案
  • 8the receiver filters messages based on all but the following:

    A.language

    B.distance

    C.culture

    D.knowledge

    E.authority/reputation

    开始考试点击查看答案
  • 9going from level 2 to level 4 in the work breakdown structure will result in

    A.less estimating accuracy

    B.better control of the project

    C.lower status reporting costs

    D.a greater likelihood that something will fall through the cracks

    E.none of the above

    开始考试点击查看答案
  • 10on november 1, $1000 worth of work on task a was supposed to have been done (bcws); however, the bcwp was $850. calculate theschedule variance:

    A.-100

    B.100

    C.-150

    D.150

    E.0.85

    开始考试点击查看答案