- 31the purpose of a dummy activity in an activity-on-arrow diagram is to:
A.identify a task that could be replaced by another.
B.take the slack time into account.
C.show a task that is not necessarily neede
D.D.denote a mileston
E.E.show a dependency relationship.
开始考试练习点击查看答案 - 32when planning, organizing, coordinating, and controlling a project an important human resources skill or ability would be
A.building multi-disciplinary teams
B.managing conflict
C.communicating orally and in writing with all levels of personnel
D.involving senior management
E.all are important
开始考试练习点击查看答案 - 33which is not a negotiation tactic、
A.imposing deadlines
B.surprises
C.person with authority is absent
D.reasoning together
E.all are negotiations tactics
开始考试练习点击查看答案 - 34which of the following is referred to as sunk cost:
A.management reserve
B.contingency fund
C.cost budgeted for construction under water
D.expended funds over which there is no further control
E.forecasted budget over-runs
开始考试练习点击查看答案 - 35a project manager believes that modifying the scope of the project may provide added value for the customer. the project manager should:
A.change the scope baseline
B.prepare a variance report
C.call a meeting of the configuration control board
D.change the project's objectives
E.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
开始考试练习点击查看答案 - 36as a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:
A.insignificant.
B.reduced.
C.unchange
D.C.unchanged.D.increased.
E.doubled.
开始考试练习点击查看答案 - 37group brainstorming encourages all of the following except:
A.team building
B.uninhibited verbalization
C.decision making
D.analysis of alternatives
E.convergent thinking
开始考试练习点击查看答案 - 38non-conformance penalties are a form of ( ).
A.quality incentive
B.risk sharing
C.contract negotiations
D.quality assurance programs
E.none of the above.
开始考试练习点击查看答案 - 39risk event status is defined as ( ) .
A.risk probability x amount at stake.
B.the severity of the consequences.
C.how likely the event is to occur with risk.
D.(cost + benefit + business risk) / insurable risk.
E.b and c
开始考试练习点击查看答案 - 40there are hard causes of conflict (e.g. conflicting schedules) and soft causes. soft causes are as important as hard causes. soft causesinclude diversity of disciplinary expertise, ( ), and the project manager's power of reward and punishment.
A.performance tradeoffs
B.ambiguity of roles
C.administrative procedures
D.determining earned value
开始考试练习点击查看答案
最新试卷
高中教育高考语文(重庆卷)2013年普通高等学校招生全国统一考试
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题9
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题8
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题6
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题4
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题3
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题2
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题1
类别:学历类其它高中教育高考语文高中语文课课练(5)
类别:学历类其它高中教育高考语文高中语文总复习 经典易错题会诊与命题角度
类别:学历类其它