位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(1,2)

methods and techniques used to examine cost and technical data are called feasibility studies. the economic aspects of a feasibility studyinclude interest rates, present worth factors, operating costs, depreciation and (    ).

发布时间:2024-07-09

A.capitalization costs.

B.technical skill requirements.

C.technology forecasting.

D.strategic marketing intelligenc

E.E.all of the above.

试卷相关题目

  • 1which contract type consists of - target costs & profit, ceiling prices and shared ratio of risk、

    A.cost plus incentive fee

    B.cost plus percentage of costs

    C.cost plus fixed fee

    D.firm fixed price

    E.firm fixed price plus incentive

    开始考试点击查看答案
  • 2the major disadvantage of a bar chart is:

    A.lack of time-phasing.

    B.cannot be related to calendar dates.

    C.does not show activity interrelationships.

    D.cannot be related to manpower planning.

    E.cannot be related to cost estimates.

    开始考试点击查看答案
  • 3the lowest dollar amount 'at stake' is associated with the following phase of the project:

    A.conceptual

    B.execution

    C.cut-over

    D.post project evaluation

    E.a and d only

    开始考试点击查看答案
  • 4the auditing function that provides feedback about the quality of output is referred to as:

    A.quality control.

    B.quality planning.

    C.quality assurance.

    D.quality improvement

    E.all of the above.

    开始考试点击查看答案
  • 5participative management:

    A.involves the solicitation of information from all team members.

    B.assumes that members avoid work and responsibility.

    C.suggests the sharing of power and decision making.

    D.employs a theory x style of leadership.

    E.a and c

    开始考试点击查看答案
  • 6standard of purchased material:

    A.simplifies inventory control

    B.reduces the risk of obsolescence

    C.reduces cost of purchasing and storage

    D.all of the abov

    E.E.a and c only.

    开始考试点击查看答案
  • 7the "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:

    A.work packages.

    B.subtasks.

    C.tasks.

    D.code of accounts.

    E.integration points.

    开始考试点击查看答案
  • 8the utility of network-based schedules:

    A.reveals interdependencies.

    B.facilitates "what if" exercises.

    C.highlights critical activities.

    D.provides information on resource requirements, time requirements and tradeoffs.

    E.all of the above.

    开始考试点击查看答案
  • 9the way a project manager sends and receives information depends upon:

    A.how others relate to the project manager

    B.the project manager's level in the organizational hierarchy

    C.the size and nature of the project

    D.the project manager's salary and age

    E.the number of projects going on at one time in the company

    开始考试点击查看答案
  • 10uncertainty refers to a situation where:

    A.the outcomes are known but their probabilities are high

    B.the outcomes and their probabilities are known

    C.neither the outcomes nor their probabilities are known

    D.states of nature can change at any time

    E.probabilities of various states of nature can change at any time

    开始考试点击查看答案
返回顶部