位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(19,20)

group brainstorming encourages all of the following except:

发布时间:2024-07-09

A.team building

B.uninhibited verbalization

C.decision making

D.analysis of alternatives

E.convergent thinking

试卷相关题目

  • 1as a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:

    A.insignificant.

    B.reduced.

    C.unchange

    D.C.unchanged.D.increased.

    E.doubled.

    开始考试点击查看答案
  • 2a project manager believes that modifying the scope of the project may provide added value for the customer. the project manager should:

    A.change the scope baseline

    B.prepare a variance report

    C.call a meeting of the configuration control board

    D.change the project's objectives

    E.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

    开始考试点击查看答案
  • 3which of the following is referred to as sunk cost:

    A.management reserve

    B.contingency fund

    C.cost budgeted for construction under water

    D.expended funds over which there is no further control

    E.forecasted budget over-runs

    开始考试点击查看答案
  • 4which is not a negotiation tactic、

    A.imposing deadlines

    B.surprises

    C.person with authority is absent

    D.reasoning together

    E.all are negotiations tactics

    开始考试点击查看答案
  • 5when planning, organizing, coordinating, and controlling a project an important human resources skill or ability would be

    A.building multi-disciplinary teams

    B.managing conflict

    C.communicating orally and in writing with all levels of personnel

    D.involving senior management

    E.all are important

    开始考试点击查看答案
  • 6non-conformance penalties are a form of (    ).

    A.quality incentive

    B.risk sharing

    C.contract negotiations

    D.quality assurance programs

    E.none of the above.

    开始考试点击查看答案
  • 7risk event status is defined as (    ) .

    A.risk probability x amount at stake.

    B.the severity of the consequences.

    C.how likely the event is to occur with risk.

    D.(cost + benefit + business risk) / insurable risk.

    E.b and c

    开始考试点击查看答案
  • 8there are hard causes of conflict (e.g. conflicting schedules) and soft causes. soft causes are as important as hard causes. soft causesinclude diversity of disciplinary expertise, (    ), and the project manager's power of reward and punishment.

    A.performance tradeoffs

    B.ambiguity of roles

    C.administrative procedures

    D.determining earned value

    开始考试点击查看答案
返回顶部