which of the following is referred to as sunk cost:

发布时间:2024-07-09

A.management reserve

B.contingency fund

C.cost budgeted for construction under water

D.expended funds over which there is no further control

E.forecasted budget over-runs

试卷相关题目

  • 1which is not a negotiation tactic、

    A.imposing deadlines

    B.surprises

    C.person with authority is absent

    D.reasoning together

    E.all are negotiations tactics

    开始考试点击查看答案
  • 2when planning, organizing, coordinating, and controlling a project an important human resources skill or ability would be

    A.building multi-disciplinary teams

    B.managing conflict

    C.communicating orally and in writing with all levels of personnel

    D.involving senior management

    E.all are important

    开始考试点击查看答案
  • 3the purpose of a dummy activity in an activity-on-arrow diagram is to:

    A.identify a task that could be replaced by another.

    B.take the slack time into account.

    C.show a task that is not necessarily neede

    D.D.denote a mileston

    E.E.show a dependency relationship.

    开始考试点击查看答案
  • 4the document authorizing functional areas to charge against the project is the:

    A.work authorization form

    B.scope baseline

    C.project charter

    D.management plan

    E.linear responsibility chart

    开始考试点击查看答案
  • 5the utility theory (    ) .

    A.considers risk propensity of the decision maker.

    B.attempts to formalize management's risk considerations.

    C.works well with decision tree analysis.

    D.is considered highly theoretical.

    E.all of the above.

    开始考试点击查看答案
  • 6a project manager believes that modifying the scope of the project may provide added value for the customer. the project manager should:

    A.change the scope baseline

    B.prepare a variance report

    C.call a meeting of the configuration control board

    D.change the project's objectives

    E.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

    开始考试点击查看答案
  • 7as a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:

    A.insignificant.

    B.reduced.

    C.unchange

    D.C.unchanged.D.increased.

    E.doubled.

    开始考试点击查看答案
  • 8group brainstorming encourages all of the following except:

    A.team building

    B.uninhibited verbalization

    C.decision making

    D.analysis of alternatives

    E.convergent thinking

    开始考试点击查看答案
  • 9non-conformance penalties are a form of (    ).

    A.quality incentive

    B.risk sharing

    C.contract negotiations

    D.quality assurance programs

    E.none of the above.

    开始考试点击查看答案
  • 10risk event status is defined as (    ) .

    A.risk probability x amount at stake.

    B.the severity of the consequences.

    C.how likely the event is to occur with risk.

    D.(cost + benefit + business risk) / insurable risk.

    E.b and c