good project objectives must be:
A.general rather than specific
B.established without considering resource bounds
C.realistic and attainable
D.overly complex
E.measurable, intangible and verifiable
试卷相关题目
- 1communication management is best described as conducting or supervising
A.the way we listen
B.the way we speak
C.the way we feel
D.the exchange of information
E.perfect documentation activities
开始考试点击查看答案 - 2a proven effective means to insure quality conformance is to:
A.delegate accountability to subordinates
B.revise quality specifications to match quality measurements
C.train workers in proper quality methods
D.inspect quality into the product
E.make quality a higher priority than cost or schedule
开始考试点击查看答案 - 3( ) is a method of procurement where a contract results from a bid which may be changed through bargaining.
A.acquisition
B.contract negotiation
C.procurement
D.purchase negotiation
E.none of the above.
开始考试点击查看答案 - 4what is the relative priority of project cost, schedule and quality、
A.1)cost - 2)schedule - 3)quality
B.1)quality - 2)schedule - 3)cost
C.1)quality - 2)cost - 3)schedule
D.1)schedule - 2)quality - 3)cost
E.all are of equal priority
开始考试点击查看答案 - 5to determine whether or not the employee correctly understands the message, the project manager needs to:
A.reduce the filtering
B.eliminate barriers
C.obtain feedback
D.use more than one medium
E.use all of the above.
开始考试点击查看答案 - 6increasing resources on the critical path activities may not always shorten the length of the project because:
A.certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).
B.safety, osha and epa may have placed restrictions on the number of people used on certain activities or in the physical location of theproject.
C.the skill level of the added resources might not be appropriate for the activities to be performe
D.D.adding more resources may create additional work and produce inefficiencies (i.
E., additional people may need training and supervision.)E.all of the above.
开始考试点击查看答案 - 7universal characteristics of effective project managers include such skills as communication, decision-making, planning, ability to identifyproblems and:
A.performing feasibility studies
B.proposal preparation
C.being close to the customer
D.maturity
E.none of the above are universal characteristics
开始考试点击查看答案 - 8which of the following is not a measure of the profitability of a project or program、
A.return on original investment.
B.net present value.
C.depreciation.
D.discounted cash flow.
E.none of the above
开始考试点击查看答案 - 9( ) is a formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology andcompensation to form the basis of a contract.
A.request for proposal
B.invitation to bid
C.request for quotation
D.intention for bid
E.none of the above.
开始考试点击查看答案 - 10by which means is a contractor able to control cost overruns due to changing requirements、
A.project data review
B.change order
C.purchase order amendment
D.change control
E.none of the above.
开始考试点击查看答案
最新试卷
房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它