- 1of the following, who has the ultimate responsibility for meeting project quality objectives、
A.project engineer
B.project manager
C.functional manager
D.quality assurance manager
E.project owner
开始考试练习点击查看答案 - 2risk mitigation involves all but which of the following:
A.developing system standards (policies, procedure, responsibility standards)
B.obtaining insurance against loss
C.identification of project risks
D.performing contingent planning
E.developing planning alternatives
开始考试练习点击查看答案 - 3the cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is:
A.payment authorization
B.bid cost considerations
C.release payment
D.back charge
E.none of the above.
开始考试练习点击查看答案 - 4the sequential steps that define the process for successfully completing a project is:
A.implementation plan
B.a life cycle
C.development plan
D.a critical path
E.management plan
开始考试练习点击查看答案 - 5which of the following time robbers end up creating additional work for the project manager and the project office、
A.failure to delegate
B.changes without notification or direction
C.unreasonable time constraints
D.over directing people
E.all of the above
开始考试练习点击查看答案 - 6you are giving your team instructions on how to perform a new test which is different from the way that the team had performed it previously.the best way to verify that the learn understands what you want is to:
A.obtain feedback
B.analyze the team's perceptions barriers
C.uses gestures in presenting the instructions
D.analyze the team's decoding skills
E.analyze the team's encoding skills
开始考试练习点击查看答案 - 7a common way by which executives provide the project manager with written authority is through:
A.a common job description for all project managers
B.an appointment letter
C.a project charter
D.all of the above
E.b and c only
开始考试练习点击查看答案 - 8surveys have shown that the primary skill needed to be a project manager is communication skill. the typical project manager spendsapproximately ( )percent of his or her time communicating.
A.40-50
B.50-60
C.60-75
D.75-90
E.90-95
开始考试练习点击查看答案 - 9the work breakdown structure (wbs) is the basis for communicating:
A.project scope, cost control, schedule, quality
B.project objectives, dependencies, plan, cost control
C.project scope, schedule, staffing, cost control
D.project scope, quality, schedule, dependencies
E.project budget, schedule, risk factors, work assignments.
开始考试练习点击查看答案 - 10the quality objectives are approved in the conceptual stage of the project by the:
A.project engineer
B.project manager
C.functional manager
D.quality assurance manager
E.project owner
开始考试练习点击查看答案
最新试卷
高中教育高考语文(重庆卷)2013年普通高等学校招生全国统一考试
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题9
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题8
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题6
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题4
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题3
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题2
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题1
类别:学历类其它高中教育高考语文高中语文课课练(5)
类别:学历类其它高中教育高考语文高中语文总复习 经典易错题会诊与命题角度
类别:学历类其它