to determine whether or not the employee correctly understands the message, the project manager needs to:

发布时间:2024-07-09

A.reduce the filtering

B.eliminate barriers

C.obtain feedback

D.use more than one medium

E.use all of the above.

一对一服务

  • 报班培训

    电网、中烟、专升本
    线下培训
  • 网课学习

    各种网络课程
    学习辅导
  • 免费资料

    免费资料
    一对一辅导
  • 老师解答

    题目不会做
    一对一辅导

试卷相关题目

  • 1the project manager must be concerned with building a closely knit team. during the project kickoff meeting, the project manager can get agood start at team building by providing the team with:

    A.proposed salary increases if the project is successful

    B.bonuses for early completion date

    C.a promise of future assignments

    D.well-defined project objectives

    E.linear responsibility charts

    开始考试点击查看答案
  • 2the budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) (    ) budget.

    A.unauditable.

    B.undistributed.

    C.preauthorize

    D.C.preauthorized.D.contingency.

    E.in-process.

    开始考试点击查看答案
  • 3researching, organizing and recording pertinent information is called:

    A.alternative analysis

    B.information gathering

    C.configuration management

    D.post project analysis

    E.all of the above

    开始考试点击查看答案
  • 4in project risk management, risk response may include actions to:

    A.reduce the probability of risk events

    B.change the scope, budget, schedule or quality specifications of the project

    C.reduce the consequences or severity of impacts of a potential risk event

    D.a and c

    E.all of the above.

    开始考试点击查看答案
  • 5a line manager provides you with three estimates for his activity in your pert network. his estimates are 2 weeks optimistically, 4 weeksmost likely, and 12 weeks pessimistically. the expected time which would appear on the chart would be:

    A.4 weeks

    B.5 weeks

    C.6 weeks

    D.7 weeks

    E.none of the above.

    开始考试点击查看答案
  • 6what is the relative priority of project cost, schedule and quality、

    A.1)cost - 2)schedule - 3)quality

    B.1)quality - 2)schedule - 3)cost

    C.1)quality - 2)cost - 3)schedule

    D.1)schedule - 2)quality - 3)cost

    E.all are of equal priority

    开始考试点击查看答案
  • 7(    ) is a method of procurement where a contract results from a bid which may be changed through bargaining.

    A.acquisition

    B.contract negotiation

    C.procurement

    D.purchase negotiation

    E.none of the above.

    开始考试点击查看答案
  • 8a proven effective means to insure quality conformance is to:

    A.delegate accountability to subordinates

    B.revise quality specifications to match quality measurements

    C.train workers in proper quality methods

    D.inspect quality into the product

    E.make quality a higher priority than cost or schedule

    开始考试点击查看答案
  • 9communication management is best described as conducting or supervising

    A.the way we listen

    B.the way we speak

    C.the way we feel

    D.the exchange of information

    E.perfect documentation activities

    开始考试点击查看答案
  • 10good project objectives must be:

    A.general rather than specific

    B.established without considering resource bounds

    C.realistic and attainable

    D.overly complex

    E.measurable, intangible and verifiable

    开始考试点击查看答案