  • 61● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.

    A.Integration

    B.Scope

    C.Configuration

    D.Requirement

    开始考试练习点击查看答案
  • 62● On some projects, especially ones of smaller scope, activity sequencing,activity resource estimating, activity duration estimating, and (70) are sotightly linked that they are viewed as a single process that can be performedby a person over a relatively short period of time.

    A.time estimating

    B.cost estimating

    C.project planning

    D.schedule development

    开始考试练习点击查看答案
  • 63● In approximating costs, the estimator considers the possible causes ofvariation of the cost estimates, including(71) .

    A.budget

    B.plan

    C.risk

    D.contract

    开始考试练习点击查看答案
  • 64● Project Quality Management must address the management of the projectand the (72) of the project. While Project Quality Management applies to allprojects, regardless of the nature of their product, product quality measuresand techniques are specific to the particular type of product produced by theproject.

    A.performance

    B.process

    C.product

    D.object

    开始考试练习点击查看答案
  • 65● (73) is a category assigned to products or services having the samefunctional use but different technical characteristics. It is not same asquality.

    A.Problem

    B.Grade

    C.Risk

    D.Defect

    开始考试练习点击查看答案
  • 66● Project (74) Management is the Knowledge Area that employs theprocesses required to ensure timely and appropriate generation, collection,distribution, storage, retrieval, and ultimate disposition of projectinformation.

    A.Integration

    B.Time

    C.Planning

    D.Communication

    开始考试练习点击查看答案
  • 67● The (75) process analyzes the effect of risk events and assigns anumerical rating to those risks.

    A.Risk Identification

    B.Quantitative Risk Analysis

    C.Qualitative Risk Analysis

    D.Risk Monitoring and Control

    开始考试练习点击查看答案