● In approximating costs, the estimator considers the possible causes ofvariation of the cost estimates, including(71) .
A.budget
B.plan
C.risk
D.contract
试卷相关题目
- 1● On some projects, especially ones of smaller scope, activity sequencing,activity resource estimating, activity duration estimating, and (70) are sotightly linked that they are viewed as a single process that can be performedby a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
开始考试点击查看答案 - 2● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.
A.Integration
B.Scope
C.Configuration
D.Requirement
开始考试点击查看答案 - 3● In the project management context, (68) includes characteristics ofunification, consolidation, articulation, and integrative actions that arecrucial to project completion, successfully meeting customer and otherstakeholder requirements, and managing expectations.
A.integration
B.scope
C.process
D.charter
开始考试点击查看答案 - 4● Organizations perform work to achieve a set of objectives. Generally,work can be categorized as either projects or operations, although the twosometimes are (67) .
A.confused
B.same
C.overlap
D.dissever
开始考试点击查看答案 - 5● (66) from one phase are usually reviewed for completeness and accuracyand approved before work starts on the next phase.
A.Process
B.Milestone
C.Work
D.Deliverables
开始考试点击查看答案 - 6● Project Quality Management must address the management of the projectand the (72) of the project. While Project Quality Management applies to allprojects, regardless of the nature of their product, product quality measuresand techniques are specific to the particular type of product produced by theproject.
A.performance
B.process
C.product
D.object
开始考试点击查看答案 - 7● (73) is a category assigned to products or services having the samefunctional use but different technical characteristics. It is not same asquality.
A.Problem
B.Grade
C.Risk
D.Defect
开始考试点击查看答案 - 8● Project (74) Management is the Knowledge Area that employs theprocesses required to ensure timely and appropriate generation, collection,distribution, storage, retrieval, and ultimate disposition of projectinformation.
A.Integration
B.Time
C.Planning
D.Communication
开始考试点击查看答案 - 9● The (75) process analyzes the effect of risk events and assigns anumerical rating to those risks.
A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring and Control
开始考试点击查看答案
最新试卷
注册安全工程师注册安全工程师安全生产管理知识2009年安全工
类别:建筑类其它注册安全工程师注册安全工程师安全生产管理知识2009年安全工
类别:建筑类其它注册安全工程师注册安全工程师安全生产管理知识2009年安全工
类别:建筑类其它注册安全工程师注册安全工程师安全生产管理知识2008年安全生
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识新安
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识安全
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识安全
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识安全
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识安全
类别:建筑类其它注册安全工程师注册安全工程师安全生产法及相关法律知识安全
类别:建筑类其它