- 71● Categories of risk response are (72).
A.Identification, quantification, response development, and responsecontrol
B.Marketing, technical, financial, and human
C.Avoidance, retention, control, and deflection
D.Avoidance, mitigation, acceptance, and Transferring
开始考试练习点击查看答案 - 72● (73)is the application of planned, systematic quality activities toensure that the project will employ all processes needed to meet requirements.
A.Quality assurance (QA)
B.Quality planning
C.Quality control (QC)
D.Quality costs
开始考试练习点击查看答案 - 73● (74) is primarily concerned with defining and controlling what is andis not included in the project.
A.Project Time Management
B.Project Cost Management
C.Project Scope management
D.Project Communications Management
开始考试练习点击查看答案 - 74● A project manager believes that modifying the scope of the project mayprovide added value service for the customer. The project manager should(75).
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project isfunded after this project is completed according to the original baseline
开始考试练习点击查看答案
最新试卷
高中教育高考语文(重庆卷)2013年普通高等学校招生全国统一考试
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题9
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题8
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题6
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题4
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题3
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题2
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题1
类别:学历类其它高中教育高考语文高中语文课课练(5)
类别:学历类其它高中教育高考语文高中语文总复习 经典易错题会诊与命题角度
类别:学历类其它