  • 71● Categories of risk response are (72).

    A.Identification, quantification, response development, and responsecontrol

    B.Marketing, technical, financial, and human

    C.Avoidance, retention, control, and deflection

    D.Avoidance, mitigation, acceptance, and Transferring

    开始考试练习点击查看答案
  • 72● (73)is the application of planned, systematic quality activities toensure that the project will employ all processes needed to meet requirements.

    A.Quality assurance (QA)

    B.Quality planning

    C.Quality control (QC)

    D.Quality costs

    开始考试练习点击查看答案
  • 73● (74) is primarily concerned with defining and controlling what is andis not included in the project.

    A.Project Time Management

    B.Project Cost Management

    C.Project Scope management

    D.Project Communications Management

    开始考试练习点击查看答案
  • 74● A project manager believes that modifying the scope of the project mayprovide added value service for the customer. The project manager should(75).

    A.assign change tasks to project members

    B.call a meeting of the configuration control board

    C.change the scope baseline

    D.postpone the modification until a separate enhancement project isfunded after this project is completed according to the original baseline

    开始考试练习点击查看答案