位置:首页 > 题库频道 > 其它分类 > 计算机其它 > 专业技术中级资格系统集成项目管理工程师基础知识2010年上半年系统集成项目管理工程师上午试卷

● (74) is primarily concerned with defining and controlling what is andis not included in the project.

发布时间:2024-07-09

A.Project Time Management

B.Project Cost Management

C.Project Scope management

D.Project Communications Management

试卷相关题目

  • 1● (73)is the application of planned, systematic quality activities toensure that the project will employ all processes needed to meet requirements.

    A.Quality assurance (QA)

    B.Quality planning

    C.Quality control (QC)

    D.Quality costs

    开始考试点击查看答案
  • 2● Categories of risk response are (72).

    A.Identification, quantification, response development, and responsecontrol

    B.Marketing, technical, financial, and human

    C.Avoidance, retention, control, and deflection

    D.Avoidance, mitigation, acceptance, and Transferring

    开始考试点击查看答案
  • 3● Project(71)is an uncertain event or condition that, if it occurs, hasa positive or a negative effect on at least one project objective, such as time,cost, scope, or quality.

    A.risk

    B.problem

    C.result

    D.data

    开始考试点击查看答案
  • 4● 项目经理在进行项目质量规划时应设计出符合项目要求的质量管理流程和标准,由此而产生的质量成本属于(70)。

    A.纠错成本

    B.预防成本

    C.评估成本

    D.缺陷成本

    开始考试点击查看答案
  • 5● CMMI所追求的过程改进目标不包括(69)。

    A.保证产品或服务质量

    B.项目时间控制

    C.所有过程都必须文档化

    D.项目成本最低

    开始考试点击查看答案
  • 6● A project manager believes that modifying the scope of the project mayprovide added value service for the customer. The project manager should(75).

    A.assign change tasks to project members

    B.call a meeting of the configuration control board

    C.change the scope baseline

    D.postpone the modification until a separate enhancement project isfunded after this project is completed according to the original baseline

    开始考试点击查看答案
返回顶部