位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(27,28)

手机扫码关注微信
随时随地刷题

项目管理师PMP美国项目管理PMPPMP认证考试练习题(27,28)

推荐等级:
  • 卷面总分:0分
  • 试卷类型:模拟试题
  • 测试费用:¥5.00
  • 试卷答案:
  • 练习次数:0
  • 作答时间:0分钟

试卷介绍

试卷预览

  • 21A task-oriented family tree of activities is a:

    A.Detailed plan.

    B.Linear responsibility chart.

    C.Work breakdown structure.

    D.Cost account coding system.

    E.Work package description.

    开始考试练习点击查看答案
  • 22Management plans include all of the following except:

    A.Organization of project.

    B.Job descriptions.

    C.Policies and procedures.

    D.Linear responsibility charts.

    E.Scope baseline.

    开始考试练习点击查看答案
  • 23A comprehensive definition of scope management would be:

    A.Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.

    B.Approval of the scope baseline.

    C.Approval of the detailed project charter.

    D.Configuration control.

    E.Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.

    开始考试练习点击查看答案
  • 24The process of choosing/documenting the best approach to achieve the project objectives is part of:

    A.The scope baseline.

    B.Scope authorization

    C.Scope definition

    D.Scope planning.

    E.All of the above.

    开始考试练习点击查看答案
  • 25A completion of a local government study resides on your critical path. This would most likely be referred to as:

    A.Soft logic

    B.Hard logic

    C.An external dependency

    D.A mandatory dependency

    E.A lost cause

    开始考试练习点击查看答案
  • 26Which of the following can affect network durations、

    A.Skills of the resource pool

    B.Calendar dates

    C.Constraints

    D.All of the above

    E.A and B only

    开始考试练习点击查看答案
  • 27Sources for data on activity durations and resource requirements can be gathered from which of the following:

    A.Past project records (historical data)

    B.Commercial techniques (standard practices, rules of thumb)

    C.Past project team members knowledge (experience, oldtimers)

    D.All of the above

    E.A and C only

    开始考试练习点击查看答案
  • 28The erection of foundation formwork before the placement of foundation concrete would be an example of a (    ) dependency.

    A.Discretionary

    B.Mandatory

    C.External

    D.Soft logic

    E.Subcontracted

    开始考试练习点击查看答案
  • 29"Hard logic" in the preparation of a network refers to:

    A.Discretionay dependencies

    B.External depenencies

    C.Mandatory dependencies

    D.All of the above

    E.A and B only

    开始考试练习点击查看答案
  • 30The difference between a project and a program is that:

    A.A program is made up of multiple projects

    B.A program requires at least three times longer to plan than a project

    C.A project is a one-shot deal while a program is on-going

    D.A and C.

    E.B and C.

    开始考试练习点击查看答案
 3/4   首页 上一页 1 2 3 4 下一页 尾页
返回顶部