- 21A task-oriented family tree of activities is a:
A.Detailed plan.
B.Linear responsibility chart.
C.Work breakdown structure.
D.Cost account coding system.
E.Work package description.
开始考试练习点击查看答案 - 22Management plans include all of the following except:
A.Organization of project.
B.Job descriptions.
C.Policies and procedures.
D.Linear responsibility charts.
E.Scope baseline.
开始考试练习点击查看答案 - 23A comprehensive definition of scope management would be:
A.Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
B.Approval of the scope baseline.
C.Approval of the detailed project charter.
D.Configuration control.
E.Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
开始考试练习点击查看答案 - 24The process of choosing/documenting the best approach to achieve the project objectives is part of:
A.The scope baseline.
B.Scope authorization
C.Scope definition
D.Scope planning.
E.All of the above.
开始考试练习点击查看答案 - 25A completion of a local government study resides on your critical path. This would most likely be referred to as:
A.Soft logic
B.Hard logic
C.An external dependency
D.A mandatory dependency
E.A lost cause
开始考试练习点击查看答案 - 26Which of the following can affect network durations、
A.Skills of the resource pool
B.Calendar dates
C.Constraints
D.All of the above
E.A and B only
开始考试练习点击查看答案 - 27Sources for data on activity durations and resource requirements can be gathered from which of the following:
A.Past project records (historical data)
B.Commercial techniques (standard practices, rules of thumb)
C.Past project team members knowledge (experience, oldtimers)
D.All of the above
E.A and C only
开始考试练习点击查看答案 - 28The erection of foundation formwork before the placement of foundation concrete would be an example of a ( ) dependency.
A.Discretionary
B.Mandatory
C.External
D.Soft logic
E.Subcontracted
开始考试练习点击查看答案 - 29"Hard logic" in the preparation of a network refers to:
A.Discretionay dependencies
B.External depenencies
C.Mandatory dependencies
D.All of the above
E.A and B only
开始考试练习点击查看答案 - 30The difference between a project and a program is that:
A.A program is made up of multiple projects
B.A program requires at least three times longer to plan than a project
C.A project is a one-shot deal while a program is on-going
D.A and C.
E.B and C.
开始考试练习点击查看答案
最新试卷
高中教育高考语文(重庆卷)2013年普通高等学校招生全国统一考试
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题9
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题8
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题6
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题4
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题3
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题2
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题1
类别:学历类其它高中教育高考语文高中语文课课练(5)
类别:学历类其它高中教育高考语文高中语文总复习 经典易错题会诊与命题角度
类别:学历类其它