位置:首页 > 题库频道 > 其它分类 > 计算机其它 > Oracle认证Oracle认证Oracle认证PA-CO

In the material master record there are three planned prices: ""Planned price 1"", ""Plannedprice2""and""Planned price 3"". What do you use them for、

发布时间:2024-07-09

A.To valuate goods movement

B.To valuate the materials in cost estimates

C.To valuate material stocks

D.To update the standard price during the release of a standard cost estimate

试卷相关题目

  • 1Which of the following statements best describe Product Cost by Period、 Note: There are 2correct answers to this question.(A). (B). (C). D). 

    A.It is used when periodic costs outweigh daily postings.

    B.It is used to analyze work in process (WIP) based on actual costs.

    C.It is used when the focus of controlling is on a stable and continuous production process.

    D.It is used in conjunction with a product cost collector.

    开始考试点击查看答案
  • 2What are the prerequisites for automatic generation of the settlement rule to a market segment for a sales order item、 Note: There are 2 correct answers to this question.

    A.The sales order item is a cost object.

    B.Profitability Analysis (CO-PA) is activated.

    C.The material in the sales order item is a service.

    D.C.The material in the sales order item is a servic

    E.D.The sales order item is assigned to a project.

    开始考试点击查看答案
  • 3How can you configure the transfer price solution in SAP S/4HANA、 Note: There are 2 correctanswers to this question.(A).(B). (C). (D). 

    A.Use separate segments for each valuation.

    B.Use separate currency types within the same ledger for each valuation.

    C.Use separate ledgers for each valuation.

    D.Use separate CO versions for each valuation.

    开始考试点击查看答案
  • 4You use a production order with Product Cost by Period and you entered a results analysiskey and variance key. How does the system calculate variances in Product Cost by Period、

    A.Variances = Target costs - Delivery value

    B.Variances = Target costs - Delivery value - WIP

    C.Variances = Actual costs - Delivery value - WIP

    D.Variances = Actual costs - Delivery value

    开始考试点击查看答案
  • 5How can you populate local variables in Profitability Analysis reports、(A). (B). (C). 

    A.By populating from user parameters

    B.By user exit

    C.By Business Add-In

    D.By user entry during report execution

    开始考试点击查看答案
  • 6You are running an indirect activity allocation. What do you post to the sender and receiver、 

    A.You post only cost to both the sender and receiver.

    B.You post quantity and cost to both the sender and receiver.

    C.You post both quantity and cost to the sender, and cost only to the receiver.

    D.You post both quantity and cost to the receiver, and cost only to the sender.

    开始考试点击查看答案
  • 7What are some of the characteristics of SAP Core Data Services (CDS) views、 Note: There are3 correct answers to this question.

    A.CDS views are considered system modifications.

    B.CDS views have ready-to-use content.

    C.CDS views duplicate data for reporting efficiencies.

    D.CDS views have no latency.

    E.CDS views support authorization.

    开始考试点击查看答案
  • 8You are setting up a direct internal activity allocation in SAP S4/HAN

    A.What is valid receiversfor the activity、 Note: There are 3 correct answers to this question.A.Profit center

    B.WBS element

    C.Sales order item

    D.Internal order

    E.General ledger account

    开始考试点击查看答案
  • 9You create a new profit center. Which company code(s) is it assigned to by default、

    A.All company codes where profit center accounting is activated.

    B.All company codes maintained in your authorization profile

    C.All company codes within the controlling area.

    D.All company codes to which the profit center standard hierarchy is assigned to.

    开始考试点击查看答案
  • 10Which field can you select for both reporting in costing based and account-based ProfitabilityAnalysis、

    A.Value in Controlling Area Currency

    B.Version

    C.Record type

    D.Cost element

    开始考试点击查看答案