位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(7.8)

company expenses such as auditing costs, supervision, office supplies, building rent and maintenance are elements of the:

发布时间:2024-07-09

A.capital budgeting process.

B.overhead rates.

C.contracts and administration costing system.

D.fringe benefits packages.

E.none of the above.

试卷相关题目

  • 1back charges refers to:

    A.transferring charges from sub-contractors to the owner

    B.adjusting payments to reflect late invoices consequence

    C.the cost of corrective action taken by the owner and charged to the contractor for non-conformance

    D.gaining restitution from the owner for non payment

    E.c and d only

    开始考试点击查看答案
  • 2which of the following is equivalent to a lump sum contract:

    A.fixed price contract

    B.price fixing contract

    C.purchase order

    D.all of the abov

    E.E.b and c only

    开始考试点击查看答案
  • 3the utility of a risk seeker is:

    A.negatively exponential

    B.positively skewed

    C.increasing

    D.decreasing

    E.symmetrical

    开始考试点击查看答案
  • 4management reserves are normally defined as a % of the total budget. as a project progresses, the project manager wants the $ value ofmanagement reserve to (    ), whereas the customer wants the management reserve to (    ).

    A.increase, increase.

    B.increase, decrease.

    C.decrease, decrease.

    D.decrease, increas

    E.E.remain the same, return to customer.

    开始考试点击查看答案
  • 5japanese quality control has improved dramatically in the last 30 years for all of the following reasons except:

    A.the use of quality circles.

    B.small, continuous improvements in quality control.

    C.the use of worker suggestion systems.

    D.the use of quality control charts.

    E.focusing quality control efforts on production outputs.

    开始考试点击查看答案
  • 6job continuity would be an example of (    ) in maslow's hierarchy of needs.

    A.self-actualization

    B.esteem

    C.physiological

    D.belonging

    E.safety

    开始考试点击查看答案
  • 7overlapping activities on a project, such as design and construction, is referred to as:

    A.fast tracking

    B.risk conversion.

    C.parallel management.

    D.process improvement.

    E.synchronous manufacturing

    开始考试点击查看答案
  • 8the major reason why a project manager would use written instead of oral communication is:

    A.documentation

    B.feedback

    C.cost

    D.barrier elimination

    E.all of the above.

    开始考试点击查看答案
  • 9the scope management provides:

    A.a basis for future decisions about the project.

    B.a baseline to accomplish verification measures.

    C.a baseline to evaluate potential scope changes.

    D.all of the abov

    E.E.b and c only.

    开始考试点击查看答案
  • 10total project risk can be defined as:

    A.the sum of the probabilities of project risks events times the sum of consequences of those risks

    B.the sum of the products of each project risk event times its consequences

    C.the sum of the consequences of all project risk events

    D.the sum of the probabilities of all project risk events

    E.1 - the sum of the probabilities of all project risk events.

    开始考试点击查看答案
返回顶部