Using the figure in the Special window, Activity "D" has a latest start time of (    ) weeks and a latest finish time of (    ) weeks.

发布时间:2024-07-09

A.2, 10

B.4, 12

C.6, 14

D.7, 15

E.9, 17

试卷相关题目

  • 1Using the figure in the Special window, The slacktime in Activity "G" is (    ) weeks.

    A.2

    B.3

    C.4

    D.5

    E.7

    开始考试点击查看答案
  • 2Resource leveling will often affect the project by making it:

    A.Shorter.

    B.Longer

    C.More responsive to customer needs.

    D.A and C.

    E.B and C.

    开始考试点击查看答案
  • 3A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. Calculate the variance:

    A.1.50%

    B.33.00%

    C.75%

    D.67%

    E.None of the above.

    开始考试点击查看答案
  • 4On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:

    A.¥-100

    B.¥100

    C.¥-150

    D.¥150

    E.85%

    开始考试点击查看答案
  • 5The purpose of a dummy activity in an activity-on-arrow diagram is to:

    A.Identify a task that could be replaced by another.

    B.Take the slack time into account.

    C.Show a task that is not necessarily neede

    D.D.Denote a mileston

    E.E.Show a dependency relationship.

    开始考试点击查看答案
  • 6Using the figure in the Special window, Activity "L" has an early start time of (    ) weeks and an early finish time of (    ) weeks.

    A.11, 13

    B.12, 14

    C.13, 15

    D.14, 16

    E.15, 17

    开始考试点击查看答案
  • 7Using the figure in the Special window, The Critical path is (    ) weeks.

    A.21

    B.22

    C.23

    D.24

    E.25

    开始考试点击查看答案
  • 8Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first、

    A.P

    B.Q

    C.R

    D.S

    E.T

    开始考试点击查看答案
  • 9Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project、

    A.0

    B.1

    C.2

    D.3

    E.4

    开始考试点击查看答案
  • 10Using the figure in the Special window, The critical path is:

    A.A-B-G

    B.C-G

    C.C-D

    D.E-F

    E.A-B-G and C-D

    开始考试点击查看答案