位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(29,30)

A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. Calculate the variance:

发布时间:2024-07-09

A.1.50%

B.33.00%

C.75%

D.67%

E.None of the above.

试卷相关题目

  • 1On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:

    A.¥-100

    B.¥100

    C.¥-150

    D.¥150

    E.85%

    开始考试点击查看答案
  • 2The purpose of a dummy activity in an activity-on-arrow diagram is to:

    A.Identify a task that could be replaced by another.

    B.Take the slack time into account.

    C.Show a task that is not necessarily neede

    D.D.Denote a mileston

    E.E.Show a dependency relationship.

    开始考试点击查看答案
  • 3As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:

    A.Insignificant.

    B.Reduced.

    C.Unchange

    D.C.Unchanged.D.Increased.

    E.Doubled.

    开始考试点击查看答案
  • 4Fast tracking means to:

    A.Speed up a project through parallel tasks.

    B.Swap one task for another.

    C.Reduce the number of tasks if possible.

    D.B and C.

    E.None of the above.

    开始考试点击查看答案
  • 5The key purpose of project control is to:

    A.Plan ahead for uncertainties.

    B.Generate status reports.

    C.Keep the project on track.

    D.Develop the project road map.

    E.All of the above.

    开始考试点击查看答案
  • 6Resource leveling will often affect the project by making it:

    A.Shorter.

    B.Longer

    C.More responsive to customer needs.

    D.A and C.

    E.B and C.

    开始考试点击查看答案
  • 7Using the figure in the Special window, The slacktime in Activity "G" is (    ) weeks.

    A.2

    B.3

    C.4

    D.5

    E.7

    开始考试点击查看答案
  • 8Using the figure in the Special window, Activity "D" has a latest start time of (    ) weeks and a latest finish time of (    ) weeks.

    A.2, 10

    B.4, 12

    C.6, 14

    D.7, 15

    E.9, 17

    开始考试点击查看答案
  • 9Using the figure in the Special window, Activity "L" has an early start time of (    ) weeks and an early finish time of (    ) weeks.

    A.11, 13

    B.12, 14

    C.13, 15

    D.14, 16

    E.15, 17

    开始考试点击查看答案
  • 10Using the figure in the Special window, The Critical path is (    ) weeks.

    A.21

    B.22

    C.23

    D.24

    E.25

    开始考试点击查看答案
返回顶部