Using the figure in the Special window, The critical path is:

发布时间:2024-07-09

A.A-B-G

B.C-G

C.C-D

D.E-F

E.A-B-G and C-D

试卷相关题目

  • 1Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project、

    A.0

    B.1

    C.2

    D.3

    E.4

    开始考试点击查看答案
  • 2Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first、

    A.P

    B.Q

    C.R

    D.S

    E.T

    开始考试点击查看答案
  • 3Using the figure in the Special window, The Critical path is (    ) weeks.

    A.21

    B.22

    C.23

    D.24

    E.25

    开始考试点击查看答案
  • 4Using the figure in the Special window, Activity "L" has an early start time of (    ) weeks and an early finish time of (    ) weeks.

    A.11, 13

    B.12, 14

    C.13, 15

    D.14, 16

    E.15, 17

    开始考试点击查看答案
  • 5Using the figure in the Special window, Activity "D" has a latest start time of (    ) weeks and a latest finish time of (    ) weeks.

    A.2, 10

    B.4, 12

    C.6, 14

    D.7, 15

    E.9, 17

    开始考试点击查看答案
  • 6The first step in building a PERT/CPM network is to:

    A.Create a flow chart

    B.Determine the critical path

    C.Show task relationships

    D.Create a work breakdown structure

    E.None of the above.

    开始考试点击查看答案
  • 7The critical path in a schedule network is the path that:

    A.Takes the longest time to complete

    B.Must be done before any other tasks

    C.Allows some flexibility in scheduling a start time.

    D.Is not affected by schedule slippage

    E.All of the above.

    开始考试点击查看答案
  • 8Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:

    A.The project's schedule will be reduced by 2 weeks.

    B.The available slack on the noncritical paths will increase.

    C.A new critical path may appear after the crash.

    D.All of the abov

    E.E.A and B.only.

    开始考试点击查看答案
  • 9Your team has prepared a CPM schedule for your review. You notice that one node has six inputs (including two dummy activities) and four outputs (which include one dummy activity). Select the correct statement from the following:

    A.This is a valid representation if the logic is correct.

    B.This is invalid because a node can have a maximum of one dummy input representation if the logic is correct.

    C.This is invalid because nodes cannot have both dummy inputs and dummy outputs.

    D.This is a invalid because the number of outputs must equal the number of inputs.

    E.This is invalid because a maximum of two inputs and two outputs are allowed using the critical path method.

    开始考试点击查看答案
  • 10During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:

    A.Now becomes the new schedule, including the changes, and the original baseline is disregarded.

    B.Is still the original baseline but annotated to reflect that a change has taken place.

    C.Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.

    D.B.Is still the original baseline but annotated to reflect that a change has taken plac

    E.C.Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.D.Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)E.Is the same since baseline schedules cannot change once the development phase is completed.

    开始考试点击查看答案