The key purpose of project control is to:

发布时间:2024-07-09

A.Plan ahead for uncertainties.

B.Generate status reports.

C.Keep the project on track.

D.Develop the project road map.

E.All of the above.

试卷相关题目

  • 1Excessive flexibility in specifying requirements will (    ) the likelihood of time overruns.

    A.Reduce.

    B.Eliminate.

    C.Double

    D.Increase

    E.Not affect

    开始考试点击查看答案
  • 2The actual configuration of a PERT/CPM network (    ) the amount of resources that can be devoted to the project.

    A.Increases.

    B.Is not affected by

    C.Does not require

    D.Is heavily dependent upon

    E.Is the only means of determining

    开始考试点击查看答案
  • 3All of the following are categories of a milestone in a schedule except:

    A.End date.

    B.Contract dates.

    C.Key events schedule

    D.D.Imposed dates.

    E.Task duration.

    开始考试点击查看答案
  • 4Using the WBS in the Special window, an instance of a work package is:

    A.Build house

    B.Excavate

    C.Prepare Foundation

    D.B and C.

    E.None of the above

    开始考试点击查看答案
  • 5Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task

    A.8

    B.8.8

    C.9.1

    D.9.7

    E.10.5

    开始考试点击查看答案
  • 6Fast tracking means to:

    A.Speed up a project through parallel tasks.

    B.Swap one task for another.

    C.Reduce the number of tasks if possible.

    D.B and C.

    E.None of the above.

    开始考试点击查看答案
  • 7As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:

    A.Insignificant.

    B.Reduced.

    C.Unchange

    D.C.Unchanged.D.Increased.

    E.Doubled.

    开始考试点击查看答案
  • 8The purpose of a dummy activity in an activity-on-arrow diagram is to:

    A.Identify a task that could be replaced by another.

    B.Take the slack time into account.

    C.Show a task that is not necessarily neede

    D.D.Denote a mileston

    E.E.Show a dependency relationship.

    开始考试点击查看答案
  • 9On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:

    A.¥-100

    B.¥100

    C.¥-150

    D.¥150

    E.85%

    开始考试点击查看答案
  • 10A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. Calculate the variance:

    A.1.50%

    B.33.00%

    C.75%

    D.67%

    E.None of the above.

    开始考试点击查看答案