位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(29,30)

The actual configuration of a PERT/CPM network (    ) the amount of resources that can be devoted to the project.

发布时间:2024-07-09

A.Increases.

B.Is not affected by

C.Does not require

D.Is heavily dependent upon

E.Is the only means of determining

试卷相关题目

  • 1All of the following are categories of a milestone in a schedule except:

    A.End date.

    B.Contract dates.

    C.Key events schedule

    D.D.Imposed dates.

    E.Task duration.

    开始考试点击查看答案
  • 2Using the WBS in the Special window, an instance of a work package is:

    A.Build house

    B.Excavate

    C.Prepare Foundation

    D.B and C.

    E.None of the above

    开始考试点击查看答案
  • 3Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task

    A.8

    B.8.8

    C.9.1

    D.9.7

    E.10.5

    开始考试点击查看答案
  • 4In crashing a task, you would focus on:

    A.As many tasks as possible.

    B.Non critical tasks.

    C.Accelerating performance of tasks on critical path.

    D.Accelerate performance by minimizing cost.

    E.A and D.

    开始考试点击查看答案
  • 5Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.

    A.0.5

    B.1

    C.1.8

    D.2.2

    E.2.8

    开始考试点击查看答案
  • 6Excessive flexibility in specifying requirements will (    ) the likelihood of time overruns.

    A.Reduce.

    B.Eliminate.

    C.Double

    D.Increase

    E.Not affect

    开始考试点击查看答案
  • 7The key purpose of project control is to:

    A.Plan ahead for uncertainties.

    B.Generate status reports.

    C.Keep the project on track.

    D.Develop the project road map.

    E.All of the above.

    开始考试点击查看答案
  • 8Fast tracking means to:

    A.Speed up a project through parallel tasks.

    B.Swap one task for another.

    C.Reduce the number of tasks if possible.

    D.B and C.

    E.None of the above.

    开始考试点击查看答案
  • 9As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:

    A.Insignificant.

    B.Reduced.

    C.Unchange

    D.C.Unchanged.D.Increased.

    E.Doubled.

    开始考试点击查看答案
  • 10The purpose of a dummy activity in an activity-on-arrow diagram is to:

    A.Identify a task that could be replaced by another.

    B.Take the slack time into account.

    C.Show a task that is not necessarily neede

    D.D.Denote a mileston

    E.E.Show a dependency relationship.

    开始考试点击查看答案
返回顶部