Line of balance charts are used most frequently in:
A.Engineering
B.Marketing
C.Manufacturing
D.Accounting
E.Contracts and procurement
试卷相关题目
- 1You are managing an internal project where a vice president from the user group is acting as the sponsor. You have just been informed by your team that the critical path has slipped by three weeks. You should:
A.Immediately inform the sponsor and ask for advice
B.Do nothing until the slippage occurs
C.See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis
D.Look for someone to blame before you see the sponsor
E.Inform your senior management of the problem and tell them that you will get back to them after you assessed the situation
开始考试点击查看答案 - 2As a control tool, the bar chart (Gantt) methods is most beneficial for:
A.rearranging conflicting tasks
B.depicting actual versus planned tasks
C.showing the outer dependencies of tasks
D.A and C.
E.A and D.
开始考试点击查看答案 - 3The difference between a project and a program is that:
A.A program is made up of multiple projects
B.A program requires at least three times longer to plan than a project
C.A project is a one-shot deal while a program is on-going
D.A and C.
E.B and C.
开始考试点击查看答案 - 4"Hard logic" in the preparation of a network refers to:
A.Discretionay dependencies
B.External depenencies
C.Mandatory dependencies
D.All of the above
E.A and B only
开始考试点击查看答案 - 5The erection of foundation formwork before the placement of foundation concrete would be an example of a ( ) dependency.
A.Discretionary
B.Mandatory
C.External
D.Soft logic
E.Subcontracted
开始考试点击查看答案 - 6Which of the following is indicative of negative float、
A.The late start date is earlier than the early start date.
B.The critical path supports the imposed end date.
C.The early finish date is equal to the late finish date.
D.When leads are employed in the schedul
E.E.The project is sinking.
开始考试点击查看答案 - 7The most frequently used construct in Precedent Diagramming Method is:
A.Start to Start.
B.Finish to Finish.
C.Start to Finish.
D.Finish to Start.
E.Dummy activity.
开始考试点击查看答案 - 8The critical path is calculated by
A.subtracting the end date of task one from the start date of task two.
B.determining which tasks have the least amount of total slack.
C.totaling the time for all activities.
D.determining the shortest path through the network.
E.Determining which tasks have the most slack
开始考试点击查看答案 - 9Using the table in the Special window, Which task is completed、
A.dig hole
B.remove debris
C.survey
D.set forms
E.place concrete
开始考试点击查看答案 - 10Which may be employed to shorten a schedule without changing the scope of the task、
A.Fast tracking.
B.Crashing
C.Releasing resources earlier from tasks which were scheduled with a late start.
D.Alter to task priorities.
E.A or B.
开始考试点击查看答案
最新试卷
房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它