You are managing an internal project where a vice president from the user group is acting as the sponsor. You have just been informed by your team that the critical path has slipped by three weeks. You should:

发布时间:2024-07-09

A.Immediately inform the sponsor and ask for advice

B.Do nothing until the slippage occurs

C.See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis

D.Look for someone to blame before you see the sponsor

E.Inform your senior management of the problem and tell them that you will get back to them after you assessed the situation

试卷相关题目

  • 1As a control tool, the bar chart (Gantt) methods is most beneficial for:

    A.rearranging conflicting tasks

    B.depicting actual versus planned tasks

    C.showing the outer dependencies of tasks

    D.A and C.

    E.A and D.

    开始考试点击查看答案
  • 2The difference between a project and a program is that:

    A.A program is made up of multiple projects

    B.A program requires at least three times longer to plan than a project

    C.A project is a one-shot deal while a program is on-going

    D.A and C.

    E.B and C.

    开始考试点击查看答案
  • 3"Hard logic" in the preparation of a network refers to:

    A.Discretionay dependencies

    B.External depenencies

    C.Mandatory dependencies

    D.All of the above

    E.A and B only

    开始考试点击查看答案
  • 4The erection of foundation formwork before the placement of foundation concrete would be an example of a (    ) dependency.

    A.Discretionary

    B.Mandatory

    C.External

    D.Soft logic

    E.Subcontracted

    开始考试点击查看答案
  • 5Sources for data on activity durations and resource requirements can be gathered from which of the following:

    A.Past project records (historical data)

    B.Commercial techniques (standard practices, rules of thumb)

    C.Past project team members knowledge (experience, oldtimers)

    D.All of the above

    E.A and C only

    开始考试点击查看答案
  • 6Line of balance charts are used most frequently in:

    A.Engineering

    B.Marketing

    C.Manufacturing

    D.Accounting

    E.Contracts and procurement

    开始考试点击查看答案
  • 7Which of the following is indicative of negative float、

    A.The late start date is earlier than the early start date.

    B.The critical path supports the imposed end date.

    C.The early finish date is equal to the late finish date.

    D.When leads are employed in the schedul

    E.E.The project is sinking.

    开始考试点击查看答案
  • 8The most frequently used construct in Precedent Diagramming Method is:

    A.Start to Start.

    B.Finish to Finish.

    C.Start to Finish.

    D.Finish to Start.

    E.Dummy activity.

    开始考试点击查看答案
  • 9The critical path is calculated by

    A.subtracting the end date of task one from the start date of task two.

    B.determining which tasks have the least amount of total slack.

    C.totaling the time for all activities.

    D.determining the shortest path through the network.

    E.Determining which tasks have the most slack

    开始考试点击查看答案
  • 10Using the table in the Special window, Which task is completed、

    A.dig hole

    B.remove debris

    C.survey

    D.set forms

    E.place concrete

    开始考试点击查看答案