位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(23,24)

Using the WBS shown in the Special window, a typical work package would be:

发布时间:2024-07-09

A.Software development

B.Systems design

C.Coding

D.A, B, and C.

E.None of the above.

试卷相关题目

  • 1Interfacing with the customer after project go-ahead is the responsibility of:

    A.Project sponsor

    B.Project team

    C.Project manager

    D.Functional manager

    E.All of the above are possible, based upon the size and complexity of the project

    开始考试点击查看答案
  • 2The "rolling wave" or "moving window" concept is used most frequently on projects where:

    A.The baseline is frozen for the duration of the project and no scope changes are permitted

    B.Marketing is unsure of what the customer actually wants and reserves the right to make major scope changes

    C.The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work

    D.Networking techniques are not appropriate

    E.All of the above

    开始考试点击查看答案
  • 3The appointment or selection of a project sponsor is often based upon:

    A.The strategic importance of the project

    B.Who the customer is

    C.Whether the organization is project or non-project-driven

    D.The profitability of the project

    E.All of the above

    开始考试点击查看答案
  • 4The most common non-behavioral reason for projects being completed behind schedule and over budget is:

    A.Selecting the wrong person as the project manager

    B.Selecting the wrong person as the sponsor

    C.Accepting a high-risk project

    D.Ill-defined requirements

    E.All of the above

    开始考试点击查看答案
  • 5The scope of a project can be expected to change if:

    A.The project manager must provide cost estimates without having a design concept

    B.Oversimplification (underestimating) of the nature of the work occurs

    C.The project manager is assigned after the project is defined, and the cost and schedule are approved

    D.A clear objective is not provided

    E.All of the above are possible based upon the situation

    开始考试点击查看答案
  • 6Feasibility studies evaluate alternatives in terms of

    A.Cost-effectiveness

    B.Ease of performance

    C.Risk

    D.Safety

    E.All or part of A through D

    开始考试点击查看答案
  • 7Project tradeoffs are usually made by comparing (    ) and constraints.

    A.Time, cost, and quality

    B.Time, risk, and quality

    C.Risk, quality, and manpower availability

    D.Cost, quality, and technical performance

    E.Cost, quality, and risk

    开始考试点击查看答案
  • 8The degree to which a company accepts and utilizes project management is often dependent upon the (    ) and (    ) of the project.

    A.Competition, dollar value

    B.Type of industry, manpower requirements

    C.Size, nature

    D.Quality requirements, manpower requirement

    E.Type of industry, risk

    开始考试点击查看答案
  • 9Project management provides organizations with a methodology to:

    A.Become more efficient and effective in accomplishing goals that cannot be handled well by the traditional structure

    B.Manage high risk repetitive work

    C.Provide clients with multiple points of contact

    D.Provide guidance in accomplishing repetitive activities

    E.All of the above

    开始考试点击查看答案
  • 10Configuration (baseline) control monitors performance against the

    A.scope baseline

    B.original schedule

    C.original budget

    D.All of the abov

    E.E.None of the above.

    开始考试点击查看答案
返回顶部