位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(1,2)

the most common types of schedules are gantt charts, milestone charts, line of balance, and:

发布时间:2024-07-09

A.networks.

B.time phased events.

C.calendar integrated activities.

D.a and c only.

E.b and c only.

试卷相关题目

  • 1the highest degrees of project risk and uncertainty are associated with the following phase of the project:

    A.conceptual

    B.execution

    C.cut-over

    D.post project evaluation

    E.a and d only

    开始考试点击查看答案
  • 2the japanese resource management model exhibits:

    A.a cooperative spirit of goal setting.

    B.non-specialized career paths

    C.frequent changes in team assignments

    D.a theory z style of management

    E.all of the above.

    开始考试点击查看答案
  • 3management plans include all of the following except:

    A.organization of project.

    B.job descriptions.

    C.policies and procedures.

    D.linear responsibility charts.

    E.scope baseline.

    开始考试点击查看答案
  • 4cost of quality is:

    A.associated with non-conformance to specifications and requirements.

    B.primarily caused by poor workmanship of workers who are building or manufacturing the product.

    C.used to determine whether a quality management program is suitable for a given project.

    D.negligible for most large projects.

    E.a and b

    开始考试点击查看答案
  • 5a variance envelope has been established on a project. the envelope goes from +-30% in r&d to +-5% during manufacturing. the reason forthe change in thickness of the envelope is because:

    A.the management reserve has been used up.

    B.the accuracy of the estimates in manufacturing are worse than the estimates in r &

    C.tighter controls are always needed as a project begins to wind down.

    D.of the personal desires of the project sponsor.

    E.of none of the above

    开始考试点击查看答案
  • 6which of the following is often overlooked in achieving effective communication、

    A.speaking clearly

    B.listening

    C.interpreting

    D.maintaining eye contact

    E.manipulating the conversation

    开始考试点击查看答案
  • 7which type of contract requires that the buyer keep the tightest labor/material cost control、

    A.cost plus incentive fee

    B.cost plus percentage of costs

    C.cost plus fixed fee

    D.firm fixed price

    E.firm fixed price plus incentive

    开始考试点击查看答案
  • 8a task-oriented family tree of activities is a:

    A.detailed plan.

    B.linear responsibility chart.

    C.work breakdown structure.

    D.cost account coding system.

    E.work package description.

    开始考试点击查看答案
  • 9adding 5 people to a 4 person team increases the communication channels by a factor of:

    A.2 times

    B.3 times

    C.4 times

    D.5 times

    E.6 times

    开始考试点击查看答案
  • 10cost management includes:

    A.cost estimating/forecasting.

    B.cost budgeting/cost control.

    C.cost applications.

    D.all of the abov

    E.E.a and b only.

    开始考试点击查看答案
返回顶部