Ethernet is the commonly used local area network communication protocol. The standard of Ethernet is <u>(72)</u>。

发布时间:2024-07-09

A.IEEE 802.1

B.IEEE 802.2

C.IEEE 802.3

D.EEE 802.11

试卷相关题目

  • 1TCP/IP communication protocol contains four layers. From bottom to top, the four layers are <u>(71)。</u>

    A.network interface layer, internet layer, transport layer and application layer

    B.internet layer, network interface layer, transport layer and application layer

    C.network interface layer, transport layer, network interface layer and application layer

    D.application layer, transport layer, internet layer and network interface layer

    开始考试点击查看答案
  • 2风险紧迫性评估多用于<u>(69)</u>中。

    A.风险识别

    B.定性风险分析

    C.定量风险分析

    D.风险应对

    开始考试点击查看答案
  • 3有关风险识别,以下说法不正确的是<u>(67)</u>。

    A.项目组全体成员参与风险识别

    B.识别范围覆盖了项目的整个生命周期

    C.风险管理计划是风险识别的输出

    D.识别过程中综合运用了多种风险识别的技术和工具

    开始考试点击查看答案
  • 4某公司对本单位负责的信息系统集成项目实施失败原因进行分析后,发现约80%的原因都是用户需求不明确、授权不清晰、以及采用了不适宜的技术,而其他十几种原因造成的失败较少。根据这些分析结果,该公司所采用项目质量控制的方法是<u>(65)</u>。

    A.散点图法

    B.直方图法

    C.帕累托法

    D.控制图法

    开始考试点击查看答案
  • 5<u>(64)</u>不是进行项目质量保证采用的方法和技术。

    A.制定质量保证规划

    B.质量活动分解

    C.建立质量保证体系

    D.统计抽样

    开始考试点击查看答案
  • 6<u>(73)</u> are the four major activities of software configuration management. ① configuration identification ② statement report ③ change control④ preparation of requirement document ⑤ configuration auditing

    A.①②③④

    B.①②④⑤

    C.①②③⑤

    D.②③④⑤

    开始考试点击查看答案
  • 7The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project ’ s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that <u>(74)</u>。

    A.the project is ahead of its planned schedule

    B.less work was completed than was planned

    C.the cost overrun for work completed

    D.the cost under-run of performance to date

    开始考试点击查看答案
  • 8SWOT analysis is a kind of risk identification method. If the project team chose the SO strategy, they should <u>(75)</u>。

    A.make full use of the advantage and catch the opportunity

    B.overcome the weakness and catch the opportunity

    C.make full use of the advantage and reduce the threat

    D.overcome the weakness and reduce the threat

    开始考试点击查看答案