A(n) (    ) is defined as a specified accomplishment in a particular instant in time which does not consume time or resources.

发布时间:2024-07-09

A.Activity

B.Event.

C.Correlation

D.Constant

E.Event constrained within planned effort.

试卷相关题目

  • 1Resource leveling (    ).

    A.Allocates resources to activities to find shortest schedule within fixed resource limits.

    B.Smoothes out resource requirements by rescheduling activities within their float time.

    C.Smooths out resource requirements by substituting activities with unassigned resources.

    D.Attempts to reduce resource requirements within a constraint on project duration

    E.B or D.

    开始考试点击查看答案
  • 2Which may be employed to shorten a schedule without changing the scope of the task、

    A.Fast tracking.

    B.Crashing

    C.Releasing resources earlier from tasks which were scheduled with a late start.

    D.Alter to task priorities.

    E.A or B.

    开始考试点击查看答案
  • 3Using the table in the Special window, Which task is completed、

    A.dig hole

    B.remove debris

    C.survey

    D.set forms

    E.place concrete

    开始考试点击查看答案
  • 4The critical path is calculated by

    A.subtracting the end date of task one from the start date of task two.

    B.determining which tasks have the least amount of total slack.

    C.totaling the time for all activities.

    D.determining the shortest path through the network.

    E.Determining which tasks have the most slack

    开始考试点击查看答案
  • 5The most frequently used construct in Precedent Diagramming Method is:

    A.Start to Start.

    B.Finish to Finish.

    C.Start to Finish.

    D.Finish to Start.

    E.Dummy activity.

    开始考试点击查看答案