位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(27,28)

Resource leveling (    ).

发布时间:2024-07-09

A.Allocates resources to activities to find shortest schedule within fixed resource limits.

B.Smoothes out resource requirements by rescheduling activities within their float time.

C.Smooths out resource requirements by substituting activities with unassigned resources.

D.Attempts to reduce resource requirements within a constraint on project duration

E.B or D.

一对一服务

  • 报班培训

    电网、中烟、专升本
    线下培训
  • 网课学习

    各种网络课程
    学习辅导
  • 免费资料

    免费资料
    一对一辅导
  • 老师解答

    题目不会做
    一对一辅导

试卷相关题目

  • 1Which may be employed to shorten a schedule without changing the scope of the task、

    A.Fast tracking.

    B.Crashing

    C.Releasing resources earlier from tasks which were scheduled with a late start.

    D.Alter to task priorities.

    E.A or B.

    开始考试点击查看答案
  • 2Using the table in the Special window, Which task is completed、

    A.dig hole

    B.remove debris

    C.survey

    D.set forms

    E.place concrete

    开始考试点击查看答案
  • 3The critical path is calculated by

    A.subtracting the end date of task one from the start date of task two.

    B.determining which tasks have the least amount of total slack.

    C.totaling the time for all activities.

    D.determining the shortest path through the network.

    E.Determining which tasks have the most slack

    开始考试点击查看答案
  • 4The most frequently used construct in Precedent Diagramming Method is:

    A.Start to Start.

    B.Finish to Finish.

    C.Start to Finish.

    D.Finish to Start.

    E.Dummy activity.

    开始考试点击查看答案
  • 5Which of the following is indicative of negative float、

    A.The late start date is earlier than the early start date.

    B.The critical path supports the imposed end date.

    C.The early finish date is equal to the late finish date.

    D.When leads are employed in the schedul

    E.E.The project is sinking.

    开始考试点击查看答案
  • 6A(n) (    ) is defined as a specified accomplishment in a particular instant in time which does not consume time or resources.

    A.Activity

    B.Event.

    C.Correlation

    D.Constant

    E.Event constrained within planned effort.

    开始考试点击查看答案
X
返回顶部