  • 61● Changes may be requested by any stakeholder involved with the project, but changescan be authorized only by (73).

    A.executive IT manager

    B.project manger

    C.change control board

    D.project sponsor

    开始考试练习点击查看答案
  • 62● Configuration management system can be used in defining approval levels forauthorizing changes and providing a method to validate approved changes.(74)  is not aproject configuration management tool.

    A.Rational Clearcase

    B.Quality Function Deployment

    C.Visual SourceSafe

    D.Concurrent Versions System

    开始考试练习点击查看答案
  • 63● Creating WBS means subdividing the major project deliverables into smallercomponents until the deliverables are defined to the  (75)  level.

    A.independent resource

    B.individual work load

    C.work milestone

    D.work package

    开始考试练习点击查看答案