- 61● Changes may be requested by any stakeholder involved with the project, but changescan be authorized only by (73).
A.executive IT manager
B.project manger
C.change control board
D.project sponsor
开始考试练习点击查看答案 - 62● Configuration management system can be used in defining approval levels forauthorizing changes and providing a method to validate approved changes.(74) is not aproject configuration management tool.
A.Rational Clearcase
B.Quality Function Deployment
C.Visual SourceSafe
D.Concurrent Versions System
开始考试练习点击查看答案 - 63● Creating WBS means subdividing the major project deliverables into smallercomponents until the deliverables are defined to the (75) level.
A.independent resource
B.individual work load
C.work milestone
D.work package
开始考试练习点击查看答案
最新试卷
高中教育高考语文(重庆卷)2013年普通高等学校招生全国统一考试
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题9
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题8
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题6
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题4
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题3
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题2
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题1
类别:学历类其它高中教育高考语文高中语文课课练(5)
类别:学历类其它高中教育高考语文高中语文总复习 经典易错题会诊与命题角度
类别:学历类其它