  • 61● The project maintains a current and approved set of requirements over the life of the project by doing thefollowing:、 (73) all changes to the requirements、 Maintaining the relationships among the requirements, the project plans, and the work products、 ……

    A.Monitoring

    B.Managing

    C.Gathering

    D.Reducing

    开始考试练习点击查看答案
  • 62● The receiving activities conduct analyses of the requirements with the requirements provider to ensure thata compatible, shared understanding is reached on the meaning of the requirements. The result of this analysisand dialog is an (74) set of requirements.

    A.agreed-to

    B.agree-to

    C.agree-to-do

    D.agree-with

    开始考试练习点击查看答案
  • 63● During the project, requirements change for a variety of reasons. As needs change and as work proceeds,additional requirements are derived and changes may have to be made to the existing requirements. It isessential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change isdocumented. The project manager may, however, want to track appropriate measures of requirementsvolatility to judge whether new or revised (75)are necessary.

    A.proceedings

    B.controls

    C.forecasting’s

    D.prelibations