手机扫码关注微信
随时随地刷题
试卷介绍
试卷预览
- 21Which of the following can be tracked using the WBS、
A.time
B.cost
C.performance
D.scope
E.None of the above.
开始考试练习点击查看答案 - 22Which of the following are types of status reports、
A.document, variance, trend and exception
B.cost, trend, schedule and acquisition
C.cost, schedule, technical performance
D.analysis, cost, performance and schedule
E.All of the above.
开始考试练习点击查看答案 - 23You have been assigned as a project leader and must first review the statement of work provided by the customer. Which of the following is most often overlooked、
A.Data item deliverables
B.Customer-furnished equipment and facilities
C.Long-lead procurement items
D.Customer-imposed milestones
E.Other subcontractor interface requirements
开始考试练习点击查看答案 - 24During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform a given task. The best way for the project manager to handle this would be to:
A.Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.
B.Let the affected line groups decide among themselves who will perform the work
C.Ask the executive sponsor to make the decision
D.Allow each line group to perform part of the task
E.All of the above
开始考试练习点击查看答案 - 25The most common definition of project success is:
A.Within time
B.Within time and cost
C.Within time, cost and technical performance requirements
D.Within time, cost, performance and accepted by the customer/user
E.None of the above
开始考试练习点击查看答案 - 26The scope of a project can be expected to change if:
A.The project manager must provide cost estimates without having a design concept
B.Oversimplification (underestimating) of the nature of the work occurs
C.The project manager is assigned after the project is defined, and the cost and schedule are approved
D.A clear objective is not provided
E.All of the above are possible based upon the situation
开始考试练习点击查看答案 - 27The most common non-behavioral reason for projects being completed behind schedule and over budget is:
A.Selecting the wrong person as the project manager
B.Selecting the wrong person as the sponsor
C.Accepting a high-risk project
D.Ill-defined requirements
E.All of the above
开始考试练习点击查看答案 - 28The appointment or selection of a project sponsor is often based upon:
A.The strategic importance of the project
B.Who the customer is
C.Whether the organization is project or non-project-driven
D.The profitability of the project
E.All of the above
开始考试练习点击查看答案 - 29The "rolling wave" or "moving window" concept is used most frequently on projects where:
A.The baseline is frozen for the duration of the project and no scope changes are permitted
B.Marketing is unsure of what the customer actually wants and reserves the right to make major scope changes
C.The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work
D.Networking techniques are not appropriate
E.All of the above
开始考试练习点击查看答案 - 30Interfacing with the customer after project go-ahead is the responsibility of:
A.Project sponsor
B.Project team
C.Project manager
D.Functional manager
E.All of the above are possible, based upon the size and complexity of the project
开始考试练习点击查看答案
最新试卷
高中教育高考语文(重庆卷)2013年普通高等学校招生全国统一考试
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题9
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题8
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题6
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题4
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题3
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题2
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题1
类别:学历类其它高中教育高考语文高中语文课课练(5)
类别:学历类其它高中教育高考语文高中语文总复习 经典易错题会诊与命题角度
类别:学历类其它