位置:首页 > 题库频道 > 其它分类 > 外语类其它 > 实用英语实用英语实用英语Fidic测试(英文试题)

Within 42 days after the Contractor became aware of the event giving rise to the claim, the Contractor shall send to the Employer a fully detailed claim. 

发布时间:2024-07-09

A.对

B.错

试卷相关题目

  • 1The Contractor shall, as specified in the Contract or as instructed by the Employer, allow appropriateopportunities for carrying out work to: 

    A.the Employer’s personnel

    B.any other contractors employed by the Employer

    C.the personnel of any legally constituted public authorities

    D.the Employer’s Representative

    开始考试点击查看答案
  • 2The Employer may claim the full amount of thePerformance Security when ()

    A.the Contractor failed to extend the validity of the Performance Security;

    B.the Contractor failed to pay the Employer an amount due, as either agreed by theContractor or determined under Sub-clause 2.5 [Employer’s Claims] or Clause 20 [Claims, Disputes and Arbitration], within 42 days after this agreement or determination,

    C.the Contractor failed to remedy a default within 28 days after receiving the Employer’s notice requiring the default to be remedied,

    D.circumstances which entitle the Employer to termination,

    开始考试点击查看答案
  • 3Employer’s Risks referred to()

    A.war hostilities

    B.pressure waves caused byaircraft,

    C.rebellion, terrorism, revolution or usurped power or civil war, within the Country,

    D.riot within the Country by the Contractor’s Personne

    开始考试点击查看答案
  • 4The Contract can be terminated when(  )

    A.the Contractor subcontracts the whole of the Works without the required agreement,

    B.the Contractor want,

    C.the execution of substantially all the Works in progress is prevented for a continuous period of 84 days by reason of Force Majeure,

    D.the Employer substantially fails to perform his obligations under the Contract,

    开始考试点击查看答案
  • 5“Force Majeure” means an exceptional event or circumstance like (  ) 

    A.which is beyond a Party’s control,

    B.war, invasion, act of foreign enemies,

    C.Which, having arisen, such Party could not reasonably have avoided or overcome,

    D.natural catastrophes such as earthquake, hurricane, typhoon or volcanic activity.

    开始考试点击查看答案
  • 6If the event or circumstance is natural catastrophes such as earthquake, hurricane, typhoon or volcanic activity, the Contractor shall be entitled to payment of any such Cost. 

    A.对

    B.错

    开始考试点击查看答案
  • 7If the Employer intends to make any material change to his financial arrangements, the Employer shall give notice to the Contractor with detailed particulars. 

    A.对

    B.错

    开始考试点击查看答案
  • 8The Engineer shall be responsible for the adequacy, stability and safety of all Site operations, of allmethods of construction and of all the Works. 

    A.对

    B.错

    开始考试点击查看答案
  • 9The Employer may appoint an Employer’s Representative to act on his behalf under the Contract.  

    A.对

    B.错

    开始考试点击查看答案
返回顶部