The Employer shall issue the Performance Certificate within ( ) days after the latest of the expiry dates of the Defects Notification Periods.
A.14
B.28
C.30
D.41
试卷相关题目
- 1Performance of the Contractor’s obligations shall not be considered to have been completed until the Employer has issued the ( ) to the Contractor.
A.Payment Certificate
B.Final Payment Certificate
C.Taking-Over Certificate
D.Performance Certificate
开始考试点击查看答案 - 2If the number is not so statedand the Parties do not agree otherwise, the DAB shall comprise ( ) persons.
A.1
B.2
C.3
D.4
开始考试点击查看答案 - 3The Employer shall give theContractor not less than ( ) hours’ notice of theEmployer’s intention to attend the tests.
A.12
B.24
C.36
D.48
开始考试点击查看答案 - 4Prior to the commencement ofthe Tests on Completion, the Contractor shall submit ( ) to the Engineere
A.drawings
B.performance security
C.the operation and maintenance manuals
D.specification
开始考试点击查看答案 - 5The () shall appoint the Contractor’s Representative and shall give him all authority necessary to act on the Contractor’s behalf under the Contract.
A.Contractor
B.Employer
C.Engineer
D.Employer’s Representative
开始考试点击查看答案 - 6“Force Majeure” means an exceptional event or circumstance like ( )
A.which is beyond a Party’s control,
B.war, invasion, act of foreign enemies,
C.Which, having arisen, such Party could not reasonably have avoided or overcome,
D.natural catastrophes such as earthquake, hurricane, typhoon or volcanic activity.
开始考试点击查看答案 - 7The Contract can be terminated when( )
A.the Contractor subcontracts the whole of the Works without the required agreement,
B.the Contractor want,
C.the execution of substantially all the Works in progress is prevented for a continuous period of 84 days by reason of Force Majeure,
D.the Employer substantially fails to perform his obligations under the Contract,
开始考试点击查看答案 - 8Employer’s Risks referred to()
A.war hostilities
B.pressure waves caused byaircraft,
C.rebellion, terrorism, revolution or usurped power or civil war, within the Country,
D.riot within the Country by the Contractor’s Personne
开始考试点击查看答案 - 9The Employer may claim the full amount of thePerformance Security when ()
A.the Contractor failed to extend the validity of the Performance Security;
B.the Contractor failed to pay the Employer an amount due, as either agreed by theContractor or determined under Sub-clause 2.5 [Employer’s Claims] or Clause 20 [Claims, Disputes and Arbitration], within 42 days after this agreement or determination,
C.the Contractor failed to remedy a default within 28 days after receiving the Employer’s notice requiring the default to be remedied,
D.circumstances which entitle the Employer to termination,
开始考试点击查看答案
最新试卷
注册安全工程师注册安全工程师安全生产事故案例分析2010年注
类别:建筑类其它注册安全工程师注册安全工程师安全生产事故案例分析2009年注
类别:建筑类其它注册安全工程师注册安全工程师安全生产事故案例分析2008年注
类别:建筑类其它注册咨询工程师注册咨询工程师项目决策分析与评价项目决策分
类别:建筑类其它注册咨询工程师注册咨询工程师项目决策分析与评价项目决策分
类别:建筑类其它注册咨询工程师注册咨询工程师项目决策分析与评价项目决策分
类别:建筑类其它注册咨询工程师注册咨询工程师项目决策分析与评价项目决策分
类别:建筑类其它注册咨询工程师注册咨询工程师项目决策分析与评价项目决策分
类别:建筑类其它注册咨询工程师注册咨询工程师项目决策分析与评价项目决策分
类别:建筑类其它注册咨询工程师注册咨询工程师项目决策分析与评价项目决策分
类别:建筑类其它