位置:首页 > 题库频道 > 其它分类 > 外语类其它 > 实用英语实用英语实用英语Fidic测试(英文试题)

If the number is not so statedand the Parties do not agree otherwise, the DAB shall comprise ( ) persons. 

发布时间:2024-07-09

A.1

B.2

C.3

D.4

试卷相关题目

  • 1The Employer shall give theContractor not less than (   ) hours’ notice of theEmployer’s intention to attend the tests. 

    A.12

    B.24

    C.36

    D.48

    开始考试点击查看答案
  • 2Prior to the commencement ofthe Tests on Completion, the Contractor shall submit  (  ) to the Engineere

    A.drawings

    B.performance security

    C.the operation and maintenance manuals

    D.specification

    开始考试点击查看答案
  • 3Performance of the Contractor’s obligations shall not be considered to have been completed until the Employer has issued the (   ) to the Contractor.

    A.Payment Certificate

    B.Final Payment Certificate

    C.Taking-Over Certificate

    D.Performance Certificate

    开始考试点击查看答案
  • 4The Employer shall issue the Performance Certificate within ( ) days after the latest of the expiry dates of the Defects Notification Periods.

    A.14

    B.28

    C.30

    D.41

    开始考试点击查看答案
  • 5The () shall appoint the Contractor’s Representative and shall give him all authority necessary to act on the Contractor’s behalf under the Contract. 

    A.Contractor

    B.Employer

    C.Engineer

    D.Employer’s Representative

    开始考试点击查看答案
  • 6“Force Majeure” means an exceptional event or circumstance like (  ) 

    A.which is beyond a Party’s control,

    B.war, invasion, act of foreign enemies,

    C.Which, having arisen, such Party could not reasonably have avoided or overcome,

    D.natural catastrophes such as earthquake, hurricane, typhoon or volcanic activity.

    开始考试点击查看答案
  • 7The Contract can be terminated when(  )

    A.the Contractor subcontracts the whole of the Works without the required agreement,

    B.the Contractor want,

    C.the execution of substantially all the Works in progress is prevented for a continuous period of 84 days by reason of Force Majeure,

    D.the Employer substantially fails to perform his obligations under the Contract,

    开始考试点击查看答案
返回顶部