位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(5.6)

risk management methodology should be adhered to in:

发布时间:2024-07-09

A.construction projects

B.system projects

C.complex projects

D.large projects

E.all of the above.

试卷相关题目

  • 1in general, attempts to smooth out period to period resources will (    ) the scheduled time and (    ) project costs.

    A.increase, decrease.

    B.increase, increase

    C.increase, increase or decrease.

    D.decrease, decreas

    E.E.decrease, increase.

    开始考试点击查看答案
  • 2which of the following activities can be considered as part of risk mitigation

    A.risk identification

    B.purchasing insurance

    C.assessment of outcomes

    D.assessment of probabilities

    E.c and d only

    开始考试点击查看答案
  • 3two sources of variation in the length of hex bolts exist. production variation and measurement error. the qc manager knows that thestandard deviation from these sources is 0.24" and 0.43" , respectively. what is the total standard deviation.

    A..10 inch.

    B..19 inch.

    C..34 inch.

    D..49 inch.

    E..67 inch.

    开始考试点击查看答案
  • 4the financial closeout of a project dictates that:

    A.all project funds have been spent.

    B.no charge numbers have been overrun.

    C.no follow-on work from this client is possible.

    D.no further charges can be made against the project.

    E.all of the above.

    开始考试点击查看答案
  • 5the comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as:

    A.post project evaluation

    B.post contract evaluation

    C.post mortem

    D.procurement performance evaluation

    E.contractor's performance evaluation

    开始考试点击查看答案
  • 6the most common form of written project communication is

    A.publications

    B.bulletin boards

    C.reports

    D.letters and memos

    E.all of the above

    开始考试点击查看答案
  • 7the most difficult decision for the executive sponsors to make at the end-of-phase review meeting is:

    A.budget allocations for the next phase.

    B.authorizing scope changes for the next phase.

    C.authorizing budget increases for the next phase based upon scope changes.

    D.canceling the project.

    E.all of the above.

    开始考试点击查看答案
  • 8the most expensive phase of life cycle costing is:

    A.r & d

    B.applied research.

    C.production

    D.operations and support.

    E.termination.

    开始考试点击查看答案
  • 9the rule of seven used by quality control engineers states that if a run of seven or more samples lays on one side of the process mean, thenthe process is out of control. what is the probability that this condition is the result of random variations.

    A.0.143

    B.0.0312

    C.0.0273

    D.0.0156

    E.0.0078

    开始考试点击查看答案
  • 10the term that best describes the 'right' to manipulate or change others is called、

    A.authority

    B.power

    C.leadership

    D.coerciveness

    E.project charter

    开始考试点击查看答案
返回顶部