the financial closeout of a project dictates that:
A.all project funds have been spent.
B.no charge numbers have been overrun.
C.no follow-on work from this client is possible.
D.no further charges can be made against the project.
E.all of the above.
试卷相关题目
- 1the comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as:
A.post project evaluation
B.post contract evaluation
C.post mortem
D.procurement performance evaluation
E.contractor's performance evaluation
开始考试点击查看答案 - 2the ability to get an individual or group to perform a given task is best described as:
A.authority
B.power
C.influence
D.leadership
E.coerciveness
开始考试点击查看答案 - 3for communication to occur, there must be:
A.two or more people involved
B.the transmittal of information
C.a communication process
D.all of the above
E.b and c only
开始考试点击查看答案 - 4assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource ( ).
A.allocation.
B.partitioning
C.leveling
D.quantification.
E.none of above.
开始考试点击查看答案 - 5a ( ) estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
A.parametric
B.definitive.
C.budget
D.bottom up.
E.top down.
开始考试点击查看答案 - 6two sources of variation in the length of hex bolts exist. production variation and measurement error. the qc manager knows that thestandard deviation from these sources is 0.24" and 0.43" , respectively. what is the total standard deviation.
A..10 inch.
B..19 inch.
C..34 inch.
D..49 inch.
E..67 inch.
开始考试点击查看答案 - 7which of the following activities can be considered as part of risk mitigation
A.risk identification
B.purchasing insurance
C.assessment of outcomes
D.assessment of probabilities
E.c and d only
开始考试点击查看答案 - 8in general, attempts to smooth out period to period resources will ( ) the scheduled time and ( ) project costs.
A.increase, decrease.
B.increase, increase
C.increase, increase or decrease.
D.decrease, decreas
E.E.decrease, increase.
开始考试点击查看答案 - 9risk management methodology should be adhered to in:
A.construction projects
B.system projects
C.complex projects
D.large projects
E.all of the above.
开始考试点击查看答案 - 10the most common form of written project communication is
A.publications
B.bulletin boards
C.reports
D.letters and memos
E.all of the above
开始考试点击查看答案
最新试卷
房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它