位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(23,24)

Project trade-offs vary between

发布时间:2024-07-09

A.risk, cost and schedule.

B.direct cost, indirect cost, and resource availability

C.quality, schedule and time

D.cost, quality and schedule

E.contract terms, scope and budget

试卷相关题目

  • 1We assign human and non-human resources in the (    ) phase of the budget.

    A.conceptual

    B.planning

    C.development

    D.implementation

    E.close-out

    开始考试点击查看答案
  • 2Project alternatives are examined during the (    ) phase of the project

    A.conceptual

    B.finish

    C.development

    D.implementation

    E.A and C.

    开始考试点击查看答案
  • 3Which of the following are included in the Acquisition phase(s) of the project life cycle.

    A.concept and development

    B.development and planning

    C.execution and phase-out

    D.planning and implementation

    E.concept and planning

    开始考试点击查看答案
  • 4Budgetary estimates are the output of the (    ) phase(s) of the project.

    A.conceptual

    B.development

    C.implementation

    D.finish

    E.All of the above.

    开始考试点击查看答案
  • 5A work breakdown structure:

    A.assures all work is identified.

    B.subdivides the project into manageable segments.

    C.provides the project sponsor with a time-phase task summary.

    D.B.subdivides the project into manageable segments.C.provides the project sponsor with a time-phase task summary.D.both A and B.

    E.All of the above.

    开始考试点击查看答案
  • 6The extent of project management techniques to be used on a project are determined mainly by the (    ) and (    ) of the project.

    A.budget, schedule

    B.quality requirements, schedule

    C.size, type of industry

    D.nature, size

    E.project manager, sponsor

    开始考试点击查看答案
  • 7The time necessary to complete a project is called the (    ) of a project.

    A.Implementation Time

    B.Life Cycle

    C.Operation Time

    D.Critical Path

    E.Completion Phase

    开始考试点击查看答案
  • 8When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

    A.task

    B.level of effort

    C.sub-task

    D.project

    E.work package

    开始考试点击查看答案
  • 9Which of the following can be tracked using the WBS、

    A.time

    B.cost

    C.performance

    D.scope

    E.None of the above.

    开始考试点击查看答案
  • 10Which of the following are types of status reports、

    A.document, variance, trend and exception

    B.cost, trend, schedule and acquisition

    C.cost, schedule, technical performance

    D.analysis, cost, performance and schedule

    E.All of the above.

    开始考试点击查看答案
返回顶部