位置:首页 > 题库频道 > 其它分类 > 资格类其它 > 项目管理师PMP美国项目管理PMPPMP认证考试练习题(23,24)

We assign human and non-human resources in the (    ) phase of the budget.

发布时间:2024-07-09

A.conceptual

B.planning

C.development

D.implementation

E.close-out

试卷相关题目

  • 1Project alternatives are examined during the (    ) phase of the project

    A.conceptual

    B.finish

    C.development

    D.implementation

    E.A and C.

    开始考试点击查看答案
  • 2Which of the following are included in the Acquisition phase(s) of the project life cycle.

    A.concept and development

    B.development and planning

    C.execution and phase-out

    D.planning and implementation

    E.concept and planning

    开始考试点击查看答案
  • 3Budgetary estimates are the output of the (    ) phase(s) of the project.

    A.conceptual

    B.development

    C.implementation

    D.finish

    E.All of the above.

    开始考试点击查看答案
  • 4A work breakdown structure:

    A.assures all work is identified.

    B.subdivides the project into manageable segments.

    C.provides the project sponsor with a time-phase task summary.

    D.B.subdivides the project into manageable segments.C.provides the project sponsor with a time-phase task summary.D.both A and B.

    E.All of the above.

    开始考试点击查看答案
  • 5The scope statement provides

    A.A basis for future decisions about a project.

    B.A baseline to accomplish verification measures.

    C.A baseline to evaluate potential scope changes.

    D.All of the above

    E.B and Conly

    开始考试点击查看答案
  • 6Project trade-offs vary between

    A.risk, cost and schedule.

    B.direct cost, indirect cost, and resource availability

    C.quality, schedule and time

    D.cost, quality and schedule

    E.contract terms, scope and budget

    开始考试点击查看答案
  • 7The extent of project management techniques to be used on a project are determined mainly by the (    ) and (    ) of the project.

    A.budget, schedule

    B.quality requirements, schedule

    C.size, type of industry

    D.nature, size

    E.project manager, sponsor

    开始考试点击查看答案
  • 8The time necessary to complete a project is called the (    ) of a project.

    A.Implementation Time

    B.Life Cycle

    C.Operation Time

    D.Critical Path

    E.Completion Phase

    开始考试点击查看答案
  • 9When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

    A.task

    B.level of effort

    C.sub-task

    D.project

    E.work package

    开始考试点击查看答案
  • 10Which of the following can be tracked using the WBS、

    A.time

    B.cost

    C.performance

    D.scope

    E.None of the above.

    开始考试点击查看答案