selection criteria for project selection include:

发布时间:2024-07-09

A.cost versus benefit

B.risk

C.contribution towards organizational goals

D.rate of return

E.all of the above.

试卷相关题目

  • 1resource leveling will often affect the project by making it:

    A.shorter.

    B.longer

    C.more responsive to customer needs.

    D.a and c

    E.b and c.

    开始考试点击查看答案
  • 2quality and (    ) are directly related.

    A.productivity

    B.cost overruns

    C.scope control

    D.pareto diagram

    E.none of the above.

    开始考试点击查看答案
  • 3advantages of the functional (hierarchical) form of organization include (    ) and creation of technicalcompetence.

    A.ease of horizontal coordination

    B.clearly defined authority

    C.high information processing capability

    D.single voice to customers

    开始考试点击查看答案
  • 4a communicator can present information using the following media except:

    A.visual

    B.audio

    C.tactile

    D.performal

    E.both a and b

    开始考试点击查看答案
  • 5(    ) best describes the goal of a project in its relationship with the customer, from initial contactthrough delivery.

    A.fitness for use

    B.customer satisfaction

    C.conformance to requirements

    D.fitness for purpose

    E.all of the above.

    开始考试点击查看答案
  • 6the statement of work (sow) is developed during the (    ) cycle.

    A.award

    B.solicitations

    C.requirements

    D.contractual

    E.requisitions

    开始考试点击查看答案
  • 7which of the following depreciation methods provides for accelerated depreciation of an asset:

    A.double declining balance.

    B.straight line.

    C.exponential depreciation

    D.double sum of the years digits

    E.double increasing balance

    开始考试点击查看答案
  • 8a plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. calculate the variance:

    A.0.015

    B.0.33

    C.0.75

    D.0.67

    E.none of the above.

    开始考试点击查看答案
  • 9a warranty may not be a remedy for products delivered unfit when (    ) .

    A.the pm has knowledge of the product, inspected it without relying on the seller's skill

    B.the products delivered comply with the plans and specifications of the client

    C.the plans and specifications produced by the seller match the completed product.

    D.a and b

    E.none of the above.

    开始考试点击查看答案
  • 10graphical displays of accumulated cost and labor hours, plotted as a function of time, are called:

    A.variance reports

    B.s curves

    C.trend analysis

    D.earned value reporting

    E.baseline control

    开始考试点击查看答案