- 1there are two major types of reserves used on projects. the ( ) is for (usually major) scope changes that were not considered as part ofthe original plan, whereas the ( ) is to compensate for minor changes in estimating, escalation factors.
A.management reserve, unplanned allowance fund.
B.management reserve, contingency.
C.contingency fund, management reserve.
D.B.management reserve, contingency.C.contingency fund, management reserv
E.D.unplanned allowance fund, budgetary reserve.E.unplanned reserve, planned reserve.
开始考试练习点击查看答案 - 2to determine what causes the majority of quality problems in a process, a very useful tool is the:
A.cause and effect diagrams.
B.flow chart.
C.control chart.
D.pareto chart.
E.trend chart.
开始考试练习点击查看答案 - 3which of the following is not part of contract administration
A.contract award
B.performance control
C.financial control
D.contract closeout
E.all of the above are parts of contract administration.
开始考试练习点击查看答案 - 4a(n) ( ) system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight,storage and loss.
A.inventory control.
B.materials management.
C.procurement.
D.all of the abov
E.E.a and c only.
开始考试练习点击查看答案 - 5expectancy theory as applied to project management implies that:
A.the team will work the hardest on those goals that are clearly explained by the project manager
B.the more rewards that the project manager provides, the better the performance of the team
C.team members will work hardest for those project goals that also bring satisfaction to personal goals
D.employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members
E.none of the above
开始考试练习点击查看答案 - 6non-verbal communication includes:
A.body movement
B.gestures
C.facial expressions
D.the way we move our hands
E.all of the above
开始考试练习点击查看答案 - 7the formal invitation to submit a price for specified goods/services is usually referred to as:
A.request for proposal
B.request for quotation
C.tender invitation
D.bid invitation
E.a and b only
开始考试练习点击查看答案 - 8the project scope/charter baseline includes:
A.summary of background conditions defining the project.
B.organization, authority and responsibility relationships.
C.functions to be performe
D.D.resource requirement schedule including time estimates.
E.all of the above.
开始考试练习点击查看答案 - 9which of the following is not an input to quality planning、
A.scope statement.
B.regulations.
C.work results.
D.standards.
E.quality policy.
开始考试练习点击查看答案 - 10which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previouselement has been completed、
A.pert
B.adm
C.pdm
D.all of the abov
E.E.a and c only.
开始考试练习点击查看答案
最新试卷
高中教育高考语文(重庆卷)2013年普通高等学校招生全国统一考试
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题9
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题8
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题6
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题4
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题3
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题2
类别:学历类其它高中教育高考语文高考语文第一轮复习测试题1
类别:学历类其它高中教育高考语文高中语文课课练(5)
类别:学历类其它高中教育高考语文高中语文总复习 经典易错题会诊与命题角度
类别:学历类其它