● Creating WBS means subdividing the major project deliverables into smallercomponents until the deliverables are defined to the  (75)  level.

发布时间:2024-07-09

A.independent resource

B.individual work load

C.work milestone

D.work package

试卷相关题目

  • 1● Configuration management system can be used in defining approval levels forauthorizing changes and providing a method to validate approved changes.(74)  is not aproject configuration management tool.

    A.Rational Clearcase

    B.Quality Function Deployment

    C.Visual SourceSafe

    D.Concurrent Versions System

    开始考试点击查看答案
  • 2● Changes may be requested by any stakeholder involved with the project, but changescan be authorized only by (73).

    A.executive IT manager

    B.project manger

    C.change control board

    D.project sponsor

    开始考试点击查看答案
  • 3● Many useful tools and techniques are used in developing schedule. (72)  is aschedule network analysis technique that modifies the project schedule to account for limitedresource.

    A.PERT

    B.Resource levelling

    C.Schedule compression

    D.Critical chain method

    开始考试点击查看答案
  • 4● Project schedule management is made up of six management processes including:activity definition, activity sequencing, ( 71) , and schedule control by order.

    A.activity duration estimating, schedule developing, activity resource estimating

    B.activity resource estimating, activity duration estimating, scheduledevelopment

    C.schedule developing, activity resource estimating, activity duration estimating

    D.activity resource estimating, schedule developing, activity duration estimating

    开始考试点击查看答案
  • 5● 甲乙丙为三个独立项目,NPV甲 =12万元,NPV乙=15万元,NPV丙=18万元,三个项目的初始投资额相同,并且回收期相同,则应优先选择(69)项目进行投资。

    A.甲

    B.乙

    C.丙

    D.甲或乙

    开始考试点击查看答案